11 Apr 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
04 Apr 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
01 Apr 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
29 Mar 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT requested to 31.07.2025. Kanhangad Proj Dn AE - 2
26 Mar 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted upto 31.03.2025. Kanhangad Proj Dn AE - 2
19 Mar 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted upto 31.03.2025. Kanhangad Proj Dn AE - 2
14 Mar 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted upto 31.03.2025. Kanhangad Proj Dn AE - 2
10 Mar 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted upto 31.03.2025. Kanhangad Proj Dn AE - 2
03 Mar 2025 Pipe to be laid:107.552 km, Pipe supplied:104.309 km, Pipe laid 60 km, HTC given 1436, Dt. of completion 03/05/2024, EOT granted upto 31.03.2025. Kanhangad Proj Dn AE - 2
03 Mar 2025 85Km pipe supplied, 50Km pipe laid,time extension applied upto 31.05.2025, CC 2nd and part bill submitted Kanhangad Proj Dn AE - 2