| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 May 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, 5th & Part bill sumbitted. | Kannur WS Sn AE 2 | |
| 09 May 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 06 May 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 03 May 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 30 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 27 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 24 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 21 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 18 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
| 15 Apr 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 |