Project | JAL JEEVAN--Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21 |
---|---|
Project Code | KLMJJM08203137P1 |
Type | Package |
Main Project | JAL JEEVAN--MISSION Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21 |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JAL JEEVAN--Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21 |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 151300000 |
TS Number | TS/2020-21/2020/16302 |
Technical specification | FHTC-8086Nos Total Line extension(pvc)-37km |
Contractor | saidax-vasco-lcgc-jv (Mob: 9447057957) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
13 Apr 2022 | Pending | Pending | Road Cut Related Risk | PWD rejected road cutting permission since road under KRFB, request submitted to KRFB on 25/03/2022 | Application resubmitted to KRFB through RoW (1035459) on 10/6/2022. To solve the road cutting related issues, District Adminstraion conducted a joint meeting at Collectrate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through RoW and also submitted hard copy of requst through e mail on 30/8/2022. | Action Taken |
11 Nov 2021 | Pending | Pending | Natural Calamities Related | work stopped due to heavy rain | No comments available. | Pending |
18 Oct 2021 | Pending | Pending | Road Cut Related Risk | Applied to PWD through Row with application no.row/1014320,24, 1014826,27 for berm cutting of Road named as Ayilara Eranoorkarikam Manali road for laying the pipe of Approx 4km but application rejected | No comments available. | Pending |
18 Oct 2021 | Pending | Pending | Road Cut Related Risk | Applied to pwd triugh row application number1014837 for berm cutting of the road named as anchal kulathuppuzha hillway highway for laying 400mtr pipes | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 16/02/2021 |
---|---|
Scheduled date of Completion as per agreement | 05 Feb 2022 |
Expected date of Completion | 04/08/2024 |
TS Date | 04 Sep 2020 |
---|---|
Estimate Approval | 04 Aug 2020 |
NIT Approval | 30 Sep 2020 |
Tender Closing | 03 Nov 2020 |
Technichal Pre-Qualification | 09 Dec 2020 |
Price bid opening | 09 Dec 2020 |
Workorder Date | 18 Dec 2020 |
---|---|
NA | 06 Feb 2021 |
Kollam Project Dn AE |
Date: 28/06/2024 |
Work in progress | 70% Completed
House connection work temporarily stopped . Total number of geotagged connections - FHTC- 4313 , HTC - 206..
Kollam Project Dn AE |
Date: 27/06/2024 |
Work in progress | 70% Completed
House connection work temporarily stopped . Total number of geotagged connections - FHTC- 4313 , HTC - 206..