JAL JEEVAN--Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21

Project JAL JEEVAN--Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21
Project Code KLMJJM08203137P1
Type Package
Main Project JAL JEEVAN--MISSION Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN--Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 151300000
TS Number TS/2020-21/2020/16302
Technical specification FHTC-8086Nos Total Line extension(pvc)-37km
Contractor saidax-vasco-lcgc-jv (Mob: 9447057957)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
13 Apr 2022 Pending Pending Road Cut Related Risk PWD rejected road cutting permission since road under KRFB, request submitted to KRFB on 25/03/2022 Application resubmitted to KRFB through RoW (1035459) on 10/6/2022. To solve the road cutting related issues, District Adminstraion conducted a joint meeting at Collectrate Conference Hall on 12/08/2022. As per direction of this meeting, application resubmitted to KRFB through RoW and also submitted hard copy of requst through e mail on 30/8/2022. Action Taken
11 Nov 2021 Pending Pending Natural Calamities Related work stopped due to heavy rain No comments available. Pending
18 Oct 2021 Pending Pending Road Cut Related Risk Applied to PWD through Row with application no.row/1014320,24, 1014826,27 for berm cutting of Road named as Ayilara Eranoorkarikam Manali road for laying the pipe of Approx 4km but application rejected No comments available. Pending
18 Oct 2021 Pending Pending Road Cut Related Risk Applied to pwd triugh row application number1014837 for berm cutting of the road named as anchal kulathuppuzha hillway highway for laying 400mtr pipes No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/02/2021
Scheduled date of Completion as per agreement 05 Feb 2022
Expected date of Completion 04/08/2024

Processing Dates

TS Date 04 Sep 2020
Estimate Approval 04 Aug 2020
NIT Approval 30 Sep 2020
Tender Closing 03 Nov 2020
Technichal Pre-Qualification 09 Dec 2020
Price bid opening 09 Dec 2020

Approval Dates

Workorder Date 18 Dec 2020
NA 06 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn AE
Date: 28/06/2024

Work in progress | 70% Completed

House connection work temporarily stopped . Total number of geotagged connections - FHTC- 4313 , HTC - 206..

Kollam Project Dn AE
Date: 27/06/2024

Work in progress | 70% Completed

House connection work temporarily stopped . Total number of geotagged connections - FHTC- 4313 , HTC - 206..