Jal Jeevan Mission (JJM)-Yeroor Phase- I -Package -4 -Construction of Proposed well cum Pumphouse near Ayiranalloor bridge, Sump cum pump house, Pressure filter & 5.5 LL OHSR at Elavaramkuzhy and its associated distribution network

Project Jal Jeevan Mission (JJM)-Yeroor Phase- I -Package -4 -Construction of Proposed well cum Pumphouse near Ayiranalloor bridge, Sump cum pump house, Pressure filter & 5.5 LL OHSR at Elavaramkuzhy and its associated distribution network
Project Code KLMJJM08203137P4
Type Package
Main Project JAL JEEVAN--MISSION Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Yeroor Phase- I -Package -4 -Construction of Proposed well cum Pumphouse near Ayiranalloor bridge, Sump cum pump house, Pressure filter & 5.5 LL OHSR at Elavaramkuzhy and its associated distribution network
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 178200000
TS Number WRD/KWA-CE(SR)/EST_TS/6094/2022_5_1_1
Technical specification Construction of 9m dia intake well near Ayiranalloor bridge, 5.5 LL OHSR at Elavaramkuzhy, 3.18 MLD Pressure filter and associated distribution network
Contractor Sivaprasad S (Mob: 9447206962)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
12 Mar 2024 Pending Pending Land Related Risk Forest land near Ayiranalloor bridge for the construction of wellcum pumphouse No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/11/2023
Scheduled date of Completion as per agreement 19 Nov 2024
Expected date of Completion 19/11/2024

Processing Dates

TS Date 13 Jul 2023
Estimate Approval 10 Jul 2023
Tender Closing 09 Aug 2023
Technichal Pre-Qualification 21 Sep 2023
Price bid opening 12 Sep 2023

Approval Dates

Workorder Date 28 Oct 2023
NA 20 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn AE
Date: 28/06/2024

Work in progress | 17% Completed

Proposed OHSR at elavarmkuzhy - Reinforcement work & shuttering work for column progressing. DI (distribution line) pipe laying progressing at ayirannalloor village . Proposed well cum pumphouse - Construction work is on hold for the permission from the forest department..

Attached images

img img

Kollam Project Dn AE
Date: 27/06/2024

Work in progress | 17% Completed

Reinforcement work & shuttering work for column progressing at elavaramkuzhy OHSR site..