Project | JJM -2020-21 Providing FHTCS in Nellaya GP |
---|---|
Project Code | PKDJJM08203246 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | This is a JJM -2020-21 Project for providing 4167 FHTCS in Nellaya GP by retrofitting |
Status | On-going |
District | Palakkad |
Executing Office | Shornur PH Dn |
AS Amount (Rs) | 62300000 |
AS Number | GO (Rt) No.541/2020/WRD/2020 |
TS Amount (Rs) | 62300000 |
TS Number | TS/2020-2021/2020/13921 |
Total Bill Submitted (Rs) | 44459833 |
Total Bill Paid (Rs) | 44459833 |
Population Benefitted | 36146 |
Capacity in MLD | 55.00 |
Actual Project Completion Date | Date is not specified |
Coverage | 4167 FHTCs |
Implementation Schedule | Download |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Feb 2024 | 3181 no FHTCs given, Pipe laying completed. Contractor submitted final bill since there is no more connection to be provided in the village under this work | Shornur PH Dn EE | |
27 Dec 2022 | 3178 no FHTCs given, Pipe laying completed. | Shornur PH Dn EE | |
23 Nov 2022 | Nellaya Phase I work 3908 FHTCs out of 4167 FHTCs given, 3668 nos geo tagged done. And additional work completed. | Shornur PH Dn EE | |
11 Oct 2022 | Additional pipe line work 6 km arranged to facilitate balance FHTC | Shoranur PH Sub Dn AEE | |
22 Jun 2022 | 70% of work completed. 2917 FHTCs out of 4167 FHTCs given. Work in progress. | Shornur PH Dn EE |
Date of start of Project | 07/11/2020 |
---|---|
Scheduled date of Completion of the Project | 21 Mar 2021 |
Expected date of Completion | 30/03/2024 |
AS Date | 21 Aug 2020 |
---|---|
TS Date | 27 Aug 2020 |
Project Officers | View |
---|