JJM -2020-21 Providing FHTCS in Nellaya GP

Project JJM -2020-21 Providing FHTCS in Nellaya GP
Project Code PKDJJM08203246
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description This is a JJM -2020-21 Project for providing 4167 FHTCS in Nellaya GP by retrofitting
Status On-going
District Palakkad
Executing Office Shornur PH Dn
AS Amount (Rs) 62300000
AS Number GO (Rt) No.541/2020/WRD/2020
TS Amount (Rs) 62300000
TS Number TS/2020-2021/2020/13921
Total Bill Submitted (Rs) 44459833
Total Bill Paid (Rs) 44459833
Population Benefitted 36146
Capacity in MLD 55.00
Actual Project Completion Date Date is not specified
Coverage 4167 FHTCs
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM 2020-2021- Providing FHTCs in Nellaya Panchayath- Phase I- Additional work- Pipe line extension for providing balance FHTCs Pattambi PH Sn
2 JJM -2020-21 Providing FHTCS in Nellaya GP Pattambi PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2024 3181 no FHTCs given, Pipe laying completed. Contractor submitted final bill since there is no more connection to be provided in the village under this work Shornur PH Dn EE
27 Dec 2022 3178 no FHTCs given, Pipe laying completed. Shornur PH Dn EE
23 Nov 2022 Nellaya Phase I work 3908 FHTCs out of 4167 FHTCs given, 3668 nos geo tagged done. And additional work completed. Shornur PH Dn EE
11 Oct 2022 Additional pipe line work 6 km arranged to facilitate balance FHTC Shoranur PH Sub Dn AEE
22 Jun 2022 70% of work completed. 2917 FHTCs out of 4167 FHTCs given. Work in progress. Shornur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 07/11/2020
Scheduled date of Completion of the Project 21 Mar 2021
Expected date of Completion 30/03/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 27 Aug 2020

Other details

Project Officers View