JJM 2020-2021- Providing FHTCs in Nellaya Panchayath- Phase I- Additional work- Pipe line extension for providing balance FHTCs

Project JJM 2020-2021- Providing FHTCs in Nellaya Panchayath- Phase I- Additional work- Pipe line extension for providing balance FHTCs
Project Code PKDJJM08203246P2
Type Package
Main Project JJM -2020-21 Providing FHTCS in Nellaya GP
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM 2020-2021- Providing FHTCs in Nellaya Panchayath- Phase I- Additional work- Pipe line extension for providing balance FHTCs
Status On-going
District Palakkad
Executing Office Pattambi PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 7000000
TS Number TS/2022-2023/2022/12787
Technical specification JJM 2020-2021- Providing FHTCs in Nellaya Panchayath- Phase I- Additional work- Pipe line extension for providing balance FHTCs
Contractor Abdul Riyas P M (Mob: 9995518035)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/06/2022
Scheduled date of Completion as per agreement 06 Jul 2022
Expected date of Completion 20/03/2023

Processing Dates

TS Date 01 Apr 2022
Estimate Approval 01 Apr 2022
NIT Approval 05 Apr 2022
Tender Closing 13 Apr 2022
Technichal Pre-Qualification 05 Apr 2022
Price bid opening 18 Apr 2022

Approval Dates

Workorder Date 07 May 2022
NA 09 May 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Pattambi PH Sn AE
Date: 01/07/2024

Work has been completed | 100% Completed

Work has been completed, 90MM PVC PIPE-6000M 80MM GI PIPE -900M laying completed.

Pattambi PH Sn AE
Date: 26/06/2024

Work has been completed | 100% Completed

Work has been completed, 90MM PVC PIPE-6000M 80MM GI PIPE -900M laying completed.