Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2024 3181 no FHTCs given, Pipe laying completed. Contractor submitted final bill since there is no more connection to be provided in the village under this work Shornur PH Dn EE
27 Dec 2022 3178 no FHTCs given, Pipe laying completed. Shornur PH Dn EE
23 Nov 2022 Nellaya Phase I work 3908 FHTCs out of 4167 FHTCs given, 3668 nos geo tagged done. And additional work completed. Shornur PH Dn EE
11 Oct 2022 Additional pipe line work 6 km arranged to facilitate balance FHTC Shoranur PH Sub Dn AEE
22 Jun 2022 70% of work completed. 2917 FHTCs out of 4167 FHTCs given. Work in progress. Shornur PH Dn EE
05 Apr 2022 68% of work completed. 2871 FHTCs out of 4167 FHTCs given. Work in progress. Shornur PH Dn EE
14 Mar 2022 2792 FHTCs out of 4167 FHTCs given. Work in progress. Shornur PH Dn EE
19 Feb 2022 70% of work completed. 2921 FHTCs out of 4167 FHTCs given. Work in progress. Shoranur PH Sub Dn AEE
19 Feb 2022 62% of work completed. 2619 FHTCs out of 4167 FHTCs given. Work in progress. Shornur PH Dn EE
15 Feb 2022 62% of work completed. 2610 FHTCs out of 4167 FHTCs given. Work in progress. Shornur PH Dn EE