Project | JJM -2020-21 Providing FHTCS in Nellaya GP |
---|---|
Project Code | PKDJJM08203246P1 |
Type | Package |
Main Project | JJM -2020-21 Providing FHTCS in Nellaya GP |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM -2020-21 Providing FHTCS in Nellaya GP |
Status | On-going |
District | Palakkad |
Executing Office | Pattambi PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 62300000 |
TS Number | TS/2020-2021/2020/13921 |
Technical specification | Nellaya |
Contractor | Rishad P M (Mob: 9895718777) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 07/11/2020 |
---|---|
Scheduled date of Completion as per agreement | 21 Mar 2021 |
Expected date of Completion | 30/03/2024 |
TS Date | 27 Aug 2020 |
---|---|
Estimate Approval | 27 Aug 2020 |
Tender Closing | 23 Aug 2020 |
Technichal Pre-Qualification | 23 Aug 2020 |
Price bid opening | 26 Aug 2020 |
Workorder Date | 22 Sep 2020 |
---|---|
NA | 06 Oct 2020 |
Pattambi PH Sn AE |
Date: 01/07/2024 |
Work in progress | 81% Completed
3181 no FHTCs given, Pipe laying completed. Contractor submitted final bill since there is no more connection to be provided in the panchayath under this work..
Pattambi PH Sn AE |
Date: 26/06/2024 |
Work in progress | 81% Completed
3181 no FHTCs given, Pipe laying completed. Contractor submitted final bill since there is no more connection to be provided in the panchayath under this work. .