AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA
AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA
Project Code
KNRAMRUT112213592
Type
Main project
Funding Agency
AMRUT
Category
AMRUT
Type of scheme
Water Supply
Scheme
AMRUT
Description
AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA
Status
On-going
District
Kannur
Executing Office
Thaliparambu WS Dn
AS Amount (Rs)
69140000
AS Number
G.O.(Rt)No.2906/2022/LSGD
TS Amount (Rs)
50900000
TS Number
14916/2022-2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date
Date is not specified
Coverage
Packages
No.
Project Name
Location
View
1
AMRUT-2.0 -TALIPARAMBA MUNCIPALITY -PACKAGE - I -CONSTRUCTION OF 1.00 LL OHSR AT PULIMPARAMBA, SUPPLYING & LAYING DISTRIBUTION NET WORK AND PROVIDING FHTCs -General Civil Work
Thaliparamba WS Sn
2
AMRUT-Taliparamba Muncipality -AMRUT 2.0 -2022-23-Construction of OHSR at Pushpagiri Laying distribution pipe line-Taliparamba Muncipality -AMRUT 2.0 -2022-23-General Civil Work
Thaliparamba WS Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
28 Sep 2026
1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Compound wall pulimbaramba pending.
Thaliparamba WS Section
02 Jul 2026
1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Balance pipe laying for 178m length completed
Thaliparamba WS Section
25 Jun 2026
1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Balance pipe laying for 178m length completed
Thaliparamba WS Section
09 Jun 2026
1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Balance pipe laying for 178m length completed
Thaliparamba WS Section
12 May 2026
1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed