| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Sep 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Compound wall pulimbaramba pending. | Thaliparamba WS Section | |
| 02 Jul 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 25 Jun 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 09 Jun 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 12 May 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 24 Apr 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 07 Apr 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 27 Mar 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 13 Mar 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 04 Mar 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section |