Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Sep 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Compound wall pulimbaramba pending. Thaliparamba WS Section
02 Jul 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
25 Jun 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
09 Jun 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri and pulimbarampa completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
12 May 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
24 Apr 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
07 Apr 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
27 Mar 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
13 Mar 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
04 Mar 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section