| Project | AMRUT-Taliparamba Muncipality -AMRUT 2.0 -2022-23-Construction of OHSR at Pushpagiri Laying distribution pipe line-Taliparamba Muncipality -AMRUT 2.0 -2022-23-General Civil Work |
|---|---|
| Project Code | KNRAMRUT112213592P2 |
| Type | Package |
| Main Project | AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-Taliparamba Muncipality -AMRUT 2.0 -2022-23-Construction of OHSR at Pushpagiri Laying distribution pipe line-Taliparamba Muncipality -AMRUT 2.0 -2022-23-General Civil Work. |
| Status | On-going |
| District | Kannur |
| Executing Office | Thaliparamba WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 13210000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/17165/2022_5_1_1 |
| Technical specification | Construction of 1LL OHSR at Pushpagiri Laying distribution pipe line. |
| Contractor | Shabeeb.V (Mob: 9048330962) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 30/07/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 29 Jan 2025 |
| Expected date of Completion | 31/07/2025 |
| TS Date | 02 Mar 2024 |
|---|---|
| Estimate Approval | 02 Mar 2024 |
| NIT Approval | 02 Mar 2024 |
| Tender Closing | 14 Mar 2024 |
| Technichal Pre-Qualification | 19 Mar 2024 |
| Price bid opening | 15 Mar 2024 |
| Workorder Date | 16 Mar 2024 |
|---|---|
| NA | 26 Jul 2024 |
| Thaliparamba WS Section |
| Date: 28/09/2026 |
Work in progress | 98% Completed
Work completed. RE on forwarded for approval.
| Thaliparamba WS Section |
| Date: 02/07/2026 |
Work in progress | 95% Completed
Interconnection work with 900mm DI pipe completed. Pipe laying balance work completed.