| Project | AMRUT-2.0 -TALIPARAMBA MUNCIPALITY -PACKAGE - I -CONSTRUCTION OF 1.00 LL OHSR AT PULIMPARAMBA, SUPPLYING & LAYING DISTRIBUTION NET WORK AND PROVIDING FHTCs -General Civil Work |
|---|---|
| Project Code | KNRAMRUT112213592P1 |
| Type | Package |
| Main Project | AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-2.0 -TALIPARAMBA MUNCIPALITY -PACKAGE - I -CONSTRUCTION OF 1.00 LL OHSR AT PULIMPARAMBA, SUPPLYING & LAYING DISTRIBUTION NET WORK AND PROVIDING FHTCs -General Civil Work |
| Status | On-going |
| District | Kannur |
| Executing Office | Thaliparamba WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 50900000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/16934/2022_5_1_1 |
| Technical specification | CONSTRUCTION OF 1.00 LL OHSR AT PULIMPARAMBA, SUPPLYING & LAYING DISTRIBUTION NET WORK AND PROVIDING FHTCs. |
| Contractor | HASCON CONSTRUCTIONS AND INTERIOR (Mob: 9847009033) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 13/06/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 12 Mar 2024 |
| Expected date of Completion | 12/09/2024 |
| TS Date | 27 Feb 2023 |
|---|---|
| Estimate Approval | 27 Feb 2023 |
| NIT Approval | 08 Mar 2023 |
| Tender Closing | 30 Mar 2023 |
| Technichal Pre-Qualification | 11 May 2023 |
| Price bid opening | 11 Apr 2023 |
| Workorder Date | 18 May 2023 |
|---|---|
| NA | 30 Jun 2023 |
| Thaliparamba WS Section |
| Date: 28/09/2026 |
Work in progress | 97% Completed
PWD Road restoration works remaining. Compound wall work pending.
| Thaliparamba WS Section |
| Date: 02/07/2026 |
Work in progress | 96% Completed
Interconnection from 800mm to 150mm DI pipe is completed. Road restoration works remaining.