JJM-Providing FHTC To Households of Erattayar and Kamakshi Panchayath

Project JJM-Providing FHTC To Households of Erattayar and Kamakshi Panchayath
Project Code IDKJJM022211324
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-Providing FHTC to Households of Erattayar and Kamakshi Panchayath
Status On-going
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 645140000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 541575733
TS Number TS/2022-2023/2022/15855
Total Bill Submitted (Rs) 44647152
Total Bill Paid (Rs) 17607000
Population Benefitted 22416
Capacity in MLD 5.00
Actual Project Completion Date 29 Feb 2024
Coverage Erattayar-5645 FHTCS Kamakshi(Part)-600 FHTCS
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Package 1- Survey and investigation works. Project Division Kattapana
2 Package 2 - Providing and Laying Distribution Network and FHTC's for various zones Project Division Kattapana
3 Package 3 - Supply and laying of RWPM and CWPM Project Division Kattapana
4 Package 4 - Supply and Laying CWPM's -200 mm D I Pipe from WTP to Hero pady ,150 mm DI Pipe from Heropady to Adayalakkallu ,80mm GI(M) pipe from Kurissummotil padi to Kurissummotil padi Top and Construction of Sump cum Pump house at Heropady.Supply and Installation of Steel Tanks at Adayalkallu,Vazhavara ,Nanguthotty and Kurissummootilpadi Top. Project Division Kattapana
5 Package 5 - Soil investigation for WTP Project Division Kattapana
6 Package 6 - Construction of new 5 MLD Water Treatment Plant Project Division Kattapana
7 PACKAGE - 7 Supply,erection,testing and commissioning of Transformer, clear water and raw water pump sets at WTP and various pump houses Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 Package 1 - Survey Work Completed. Package 2 - 7941M - 90 MM HDPE PN 8, 7751 M - 90 MM HDPE PN 16 ,6201M - 90 MM HDPE PN 10, 110 MM HDPE PN 16 -14513M , 110 MM HDPE PN 8 - 12127M ,110 MM HDPE PN 10 -1727 m , 80 mm GI PIPES LAID -17111M ,78 M - 100 mm GI PIPES LAID. Package 3 - 2190.55 m 200mm Dia DI pipe laid at kurishumoottilpady site, package 4 - Agreement executed on 22.11.2023 , Package 5-Soil Investigation for WTP Completed , Package 6 - work under design stage due to foundation bearing capacity , Package 7 - Recasted estimate For Estimate approval at CE office on 6.12.2023 Kattapana AE 1
24 Jun 2024 Package 1 - Survey Work Completed. Package 2 - 7941M - 90 MM HDPE PN 8, 7751 M - 90 MM HDPE PN 16 ,6201M - 90 MM HDPE PN 10, 110 MM HDPE PN 16 -14513M , 110 MM HDPE PN 8 - 12127M ,110 MM HDPE PN 10 -1727 m , 80 mm GI PIPES LAID -17111M ,78 M - 100 mm GI PIPES LAID. Package 3 - 2190.55 m 200mm Dia DI pipe laid at kurishumoottilpady site, package 4 - Agreement executed on 22.11.2023 , Package 5-Soil Investigation for WTP Completed , Package 6 - work under design stage due to foundation bearing capacity , Package 7 - Recasted estimate For Estimate approval at CE office on 6.12.2023 Kattappana AEE 1
20 Jun 2024 Package 1 - Survey Work Completed. Package 2 - 7941M - 90 MM HDPE PN 8, 7751 M - 90 MM HDPE PN 16 ,6201M - 90 MM HDPE PN 10, 110 MM HDPE PN 16 -14513M , 110 MM HDPE PN 8 - 12127M ,110 MM HDPE PN 10 -1727 m , 80 mm GI PIPES LAID -17111M ,78 M - 100 mm GI PIPES LAID. Package 3 - 2190.55 m 200mm Dia DI pipe laid at kurishumoottilpady site, package 4 - Agreement executed on 22.11.2023 , Package 5-Soil Investigation for WTP Completed , Package 6 - work under design stage due to foundation bearing capacity , Package 7 - Recasted estimate For Estimate approval at CE office on 6.12.2023 Kattappana AEE 1
17 Jun 2024 Package 1 - Survey Work Completed. Package 2 - 7941M - 90 MM HDPE PN 8, 7751 M - 90 MM HDPE PN 16 ,6201M - 90 MM HDPE PN 10, 110 MM HDPE PN 16 -14513M , 110 MM HDPE PN 8 - 12127M ,110 MM HDPE PN 10 -1727 m , 80 mm GI PIPES LAID -17111M ,78 M - 100 mm GI PIPES LAID. Package 3 - 2190.55 m 200mm Dia DI pipe laid at kurishumoottilpady site, package 4 - Agreement executed on 22.11.2023 , Package 5-Soil Investigation for WTP Completed , Package 6 - work under design stage due to foundation bearing capacity , Package 7 - Recasted estimate For Estimate approval at CE office on 6.12.2023 Kattappana AEE 1
13 Jun 2024 Package 1 - Survey Work Completed. Package 2 - 7941M - 90 MM HDPE PN 8, 7751 M - 90 MM HDPE PN 16 ,6201M - 90 MM HDPE PN 10, 110 MM HDPE PN 16 -14513M , 110 MM HDPE PN 8 - 12127M ,110 MM HDPE PN 10 -1727 m , 80 mm GI PIPES LAID -17111M ,78 M - 100 mm GI PIPES LAID. Package 3 - 2190.55 m 200mm Dia DI pipe laid at kurishumoottilpady site, package 4 - Agreement executed on 22.11.2023 , Package 5-Soil Investigation for WTP Completed , Package 6 - work under design stage due to foundation bearing capacity , Package 7 - Recasted estimate For Estimate approval at CE office on 6.12.2023 Kattappana AEE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/10/2022
Scheduled date of Completion of the Project 29 Mar 2024
Expected date of Completion 30/03/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 27 Apr 2022

Other details

Project Officers View