Package 4 - Supply and Laying CWPM's -200 mm D I Pipe from WTP to Hero pady ,150 mm DI Pipe from Heropady to Adayalakkallu ,80mm GI(M) pipe from Kurissummotil padi to Kurissummotil padi Top and Construction of Sump cum Pump house at Heropady.Supply and Installation of Steel Tanks at Adayalkallu,Vazhavara ,Nanguthotty and Kurissummootilpadi Top.
Project |
Package 4 - Supply and Laying CWPM's -200 mm D I Pipe from WTP to Hero pady ,150 mm DI Pipe from Heropady to Adayalakkallu ,80mm GI(M) pipe from Kurissummotil padi to Kurissummotil padi Top and Construction of Sump cum Pump house at Heropady.Supply and Installation of Steel Tanks at Adayalkallu,Vazhavara ,Nanguthotty and Kurissummootilpadi Top. |
Project Code |
IDKJJM022211324P4 |
Type |
Package |
Main Project |
JJM-Providing FHTC To Households of Erattayar and Kamakshi Panchayath
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Supply and Laying CWPM's -200 mm D I Pipe from WTP to Hero pady ,150 mm DI Pipe from Heropady to Adayalakkallu ,80mm GI(M) pipe from Kurissummotil padi to Kurissummotil padi Top and Construction of Sump cum Pump house at Heropady.Supply and Installation of Steel Tanks at Adayalkallu,Vazhavara ,Nanguthotty and Kurissummootilpadi Top.
|
Status |
On-going |
District |
Idukki |
Executing Office |
Kattappana Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
34810000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/822/2022_26_2_1 |
Technical specification |
FHTCS NUMBER - KAMAKSHI - 600 nos
ERATTAYAR - 5645 nos
Total Pipe and Length and size- 80mm GI - 39775,
90mm HDPE PN8 - 10205, 90mm HDPE P10 - 8100 , 90mm HDPE PN 16 - 8798 , 110 mm HDPE PN 10 - 10128 ,110 mm HDPE PN 16 -28335,
150 mm DI - 4696 , 200 mm DI - 1115 , 250mm DI - 635 ,
100 MM GI for crossing - 360 , 250 FCV -3,200 FCV-5,
150 FCV-9,100 Valve-70,80 Valve-95 TOTAL PIPIE - 139440 M |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
17/12/2022 |
Scheduled date of Completion as per agreement |
02 Dec 2024 |
Expected date of Completion |
30/03/2024 |
Processing Dates
TS Date |
26 Oct 2022 |
Estimate Approval |
26 Oct 2022 |
NIT Approval |
28 Oct 2022 |
Tender Closing |
27 Jul 2023 |
Technichal Pre-Qualification |
26 Oct 2022 |
Price bid opening |
14 Aug 2023 |
Approval Dates
Workorder Date |
22 Nov 2023 |
NA |
02 Dec 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kattappana AEE 1 |
Date: 28/06/2024 |
Work has started | 0% Completed
Agreement executed on 22.11.2023.
Kattapana AE 1 |
Date: 27/06/2024 |
Work in progress | 0% Completed
Agreement executed on 22.11.2023.