Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Package 4 - Supply and Laying CWPM's -200 mm D I Pipe from WTP to Hero pady ,150 mm DI Pipe from Heropady to Adayalakkallu ,80mm GI(M) pipe from Kurissummotil padi to Kurissummotil padi Top and Construction of Sump cum Pump house at Heropady.Supply and Installation of Steel Tanks at Adayalkallu,Vazhavara ,Nanguthotty and Kurissummootilpadi Top.

Project Package 4 - Supply and Laying CWPM's -200 mm D I Pipe from WTP to Hero pady ,150 mm DI Pipe from Heropady to Adayalakkallu ,80mm GI(M) pipe from Kurissummotil padi to Kurissummotil padi Top and Construction of Sump cum Pump house at Heropady.Supply and Installation of Steel Tanks at Adayalkallu,Vazhavara ,Nanguthotty and Kurissummootilpadi Top.
Project Code IDKJJM022211324P4
Type Package
Main Project JJM-Providing FHTC To Households of Erattayar and Kamakshi Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Supply and Laying CWPM's -200 mm D I Pipe from WTP to Hero pady ,150 mm DI Pipe from Heropady to Adayalakkallu ,80mm GI(M) pipe from Kurissummotil padi to Kurissummotil padi Top and Construction of Sump cum Pump house at Heropady.Supply and Installation of Steel Tanks at Adayalkallu,Vazhavara ,Nanguthotty and Kurissummootilpadi Top.
Status On-going
District Idukki
Executing Office Kattappana Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 34810000
TS Number WRD/KWA-CE(CR)/EST_TS/822/2022_26_2_1
Technical specification FHTCS NUMBER - KAMAKSHI - 600 nos ERATTAYAR - 5645 nos Total Pipe and Length and size- 80mm GI - 39775, 90mm HDPE PN8 - 10205, 90mm HDPE P10 - 8100 , 90mm HDPE PN 16 - 8798 , 110 mm HDPE PN 10 - 10128 ,110 mm HDPE PN 16 -28335, 150 mm DI - 4696 , 200 mm DI - 1115 , 250mm DI - 635 , 100 MM GI for crossing - 360 , 250 FCV -3,200 FCV-5, 150 FCV-9,100 Valve-70,80 Valve-95 TOTAL PIPIE - 139440 M

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/12/2022
Scheduled date of Completion as per agreement 02 Dec 2024
Expected date of Completion 30/03/2024

Processing Dates

TS Date 26 Oct 2022
Estimate Approval 26 Oct 2022
NIT Approval 28 Oct 2022
Tender Closing 27 Jul 2023
Technichal Pre-Qualification 26 Oct 2022
Price bid opening 14 Aug 2023

Approval Dates

Workorder Date 22 Nov 2023
NA 02 Dec 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana AEE 1
Date: 28/06/2024

Work has started | 0% Completed

Agreement executed on 22.11.2023.

Kattapana AE 1
Date: 27/06/2024

Work in progress | 0% Completed

Agreement executed on 22.11.2023.