Package 2 - Providing and Laying Distribution Network and FHTC's for various zones

Project Package 2 - Providing and Laying Distribution Network and FHTC's for various zones
Project Code IDKJJM022211324P2
Type Package
Main Project JJM-Providing FHTC To Households of Erattayar and Kamakshi Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM PROVIDING FHTCS TO ALL HOUSEHOLD IN ERATTAYAR AND KAMAKSHI (PART) PANCHAYATHS IN IDUKKI DISTRICTS - Providing and Laying Distribution Network and FHTC's for various zones
Status On-going
District Idukki
Executing Office Kattappana Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 352065156
TS Number WRD/KWA-CE(CR)/EST_TS/822/2022_26_3_2
Technical specification FHTCS NUMBER - KAMAKSHI - 600 nos ERATTAYAR - 5645 nos Total Pipe and Length and size- 80mm GI - 39775, 90mm HDPE PN8 - 10205, 90mm HDPE P10 - 8100 , 90mm HDPE PN 16 - 8798 , 110 mm HDPE PN 10 - 10128 ,110 mm HDPE PN 16 -28335, 150 mm DI - 4696 , 200 mm DI - 1115 , 250mm DI - 635 , 100 MM GI for crossing - 360 , 250 FCV -3,200 FCV-5, 150 FCV-9,100 Valve-70,80 Valve-95 TOTAL PIPIE - 139440 M

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 26/11/2022
Scheduled date of Completion as per agreement 08 Mar 2024
Expected date of Completion 30/03/2024

Processing Dates

TS Date 21 Oct 2022
Estimate Approval 21 Oct 2022
NIT Approval 09 Nov 2022
Tender Closing 24 Dec 2022
Technichal Pre-Qualification 31 Dec 2022
Price bid opening 14 Jan 2022

Approval Dates

Workorder Date 16 Feb 2023
NA 08 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattapana AE 1
Date: 27/06/2024

Work in progress | 48% Completed

7941M - 90 MM HDPE PN 8, 7751 M - 90 MM HDPE PN 16 ,6201M - 90 MM HDPE PN 10, 110 MM HDPE PN 16 -14,513M , 110 MM HDPE PN 8 - 12127M ,110 MM HDPE PN 10 -1727 m , 80 mm GI PIPES LAID -17111M ,78 M - 100 mm GI PIPES LAID. Road restoration work in Progress.

Kattapana AE 1
Date: 26/06/2024

Work in progress | 48% Completed

7941M - 90 MM HDPE PN 8, 7751 M - 90 MM HDPE PN 16 ,6201M - 90 MM HDPE PN 10, 110 MM HDPE PN 16 -14,513M , 110 MM HDPE PN 8 - 12127M ,110 MM HDPE PN 10 -1727 m , 80 mm GI PIPES LAID -17111M ,78 M - 100 mm GI PIPES LAID. Road restoration work in Progress.