Package 6 - Construction of new 5 MLD Water Treatment Plant

Project Package 6 - Construction of new 5 MLD Water Treatment Plant
Project Code IDKJJM022211324P6
Type Package
Main Project JJM-Providing FHTC To Households of Erattayar and Kamakshi Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM PROVIDING FHTCS TO ALL HOUSEHOLD IN ERATTAYAR AND KAMAKSHI (PART) PANCHAYATHS IN IDUKKI DISTRICTS- Construction of new 5 MLD Water Treatment Plant
Status On-going
District Idukki
Executing Office Kattappana Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 50300576
TS Number WRD/KWA-CE(CR)/EST_TS/822/2022_4_1_1
Technical specification FHTCS NUMBER - KAMAKSHI - 600 nos ERATTAYAR - 5645 nos Total Pipe and Length and size- 80mm GI - 39775, 90mm HDPE PN8 - 10205, 90mm HDPE P10 - 8100 , 90mm HDPE PN 16 - 8798 , 110 mm HDPE PN 10 - 10128 ,110 mm HDPE PN 16 -28335, 150 mm DI - 4696 , 200 mm DI - 1115 , 250mm DI - 635 , 100 MM GI for crossing - 360 , 250 FCV -3,200 FCV-5, 150 FCV-9,100 Valve-70,80 Valve-95 TOTAL PIPIE - 139440 M

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/12/2022
Scheduled date of Completion as per agreement 30 Mar 2024
Expected date of Completion 30/03/2024

Processing Dates

TS Date 19 Nov 2022
Estimate Approval 19 Nov 2022
NIT Approval 29 Mar 2023
Tender Closing 28 Apr 2023
Technichal Pre-Qualification 04 Apr 2023
Price bid opening 04 Apr 2023

Approval Dates

Workorder Date 15 Jul 2023
NA 19 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana AEE 1
Date: 28/06/2024

Work in progress | 2% Completed

work under design stage due to foundation bearing capacity..

Kattapana AE 1
Date: 27/06/2024

Work in progress | 2% Completed

work under design stage due to foundation bearing capacity..