JJM 2020-21- Vellavoor Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC

Project JJM 2020-21- Vellavoor Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC
Project Code KTMJJM08204284
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Laying 23km distribution lines and providing 1500 FHTcs
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 263700000
AS Number GO (Rt)No541/2020/WRD
TS Amount (Rs) 62700000
TS Number TS/2020-2021/2020/19273
Total Bill Submitted (Rs) 28509397
Total Bill Paid (Rs) 28509397
Population Benefitted 6000
Capacity in MLD 9.00
Actual Project Completion Date 31 Mar 2022
Coverage Vellavoor Panchayath(Part)
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM- 2020-21 - KOTTAYAM DISTRICT - WSS TO VELLAVOOR PANCHAYAT - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I - Package 3 Kottayam Project Dn
2 JJM- 2020-21 - KOTTAYAM DISTRICT - WSS TO VELLAVOOR PANCHAYAT - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I, ZONE - I DMA II and III - Package 4 Kottayam Project Dn
3 JJM- 2020-21 - VELLAVOOR PANCHAYATH- KOTTAYAM DISTRICT - Phase I- PACKAGE 2 - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I - Road Restoration of PWD roads after pipe laying Kottayam Project Dn
4 JM 2021-22 - Vellavoor Panchayath - Phase IV - Package 1-Supplying and laying distribution lines and providing FHTCs. Kottayam Project Dn
5 Package I - JJM Vellavorr panchayat Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Feb 2022 18000m/22800m laying completed. 387/1500 FHTC completed and in progress. PWD rejected 2 roads under DLP and are included in the estimate for new packages with GI as per the direction of MLA and the pipes were relocated to other panchayath roads. Kottayam Project Dn AE1
10 Nov 2021 9626m/22800m Laying completed. 341/1500 fhtc given. Work in progress where PWD issued sanction. Rejected 3 Roads due to DLP. Contractors request for extending time of completion up to 31/03/2022 expectin sabrimala seasonal ban on road cutting up to 15/01/2022 forwarded to higher office Kottayam Project Dn AE1
09 Nov 2021 Contractor given request for time extension upto 31.03.2022 Kottayam Project Dn EE
01 Oct 2021 Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. Kottayam AE 3
10 Sep 2021 7894m/22800m Laying completed. 341/1500 fhtc given Balance can be done after getting the road cutting sanction from PWD. RR charges remitted and expecting before 15th September. Kottayam Project Dn AE1

Project Review

See All Review messages
Review Date Review Message Review Attended By
24 Jun 2021 Add dated photographs Documents related to road issues EE,AEE,AE
11 Feb 2021 ADD PACKAGE II AE,EE

Duration & Sanction dates

Date of start of Project 21/11/2020
Scheduled date of Completion of the Project 05 May 2021
Expected date of Completion 29/06/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 08 Sep 2020

Other details