Project | JJM 2020-21- Vellavoor Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC |
---|---|
Project Code | KTMJJM08204284 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Laying 23km distribution lines and providing 1500 FHTcs |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
AS Amount (Rs) | 263700000 |
AS Number | GO (Rt)No541/2020/WRD |
TS Amount (Rs) | 62700000 |
TS Number | TS/2020-2021/2020/19273 |
Total Bill Submitted (Rs) | 28509397 |
Total Bill Paid (Rs) | 28509397 |
Population Benefitted | 6000 |
Capacity in MLD | 9.00 |
Actual Project Completion Date | 31 Mar 2022 |
Coverage | Vellavoor Panchayath(Part) |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | JJM- 2020-21 - KOTTAYAM DISTRICT - WSS TO VELLAVOOR PANCHAYAT - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I - Package 3 | Kottayam Project Dn | |
2 | JJM- 2020-21 - KOTTAYAM DISTRICT - WSS TO VELLAVOOR PANCHAYAT - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I, ZONE - I DMA II and III - Package 4 | Kottayam Project Dn | |
3 | JJM- 2020-21 - VELLAVOOR PANCHAYATH- KOTTAYAM DISTRICT - Phase I- PACKAGE 2 - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I - Road Restoration of PWD roads after pipe laying | Kottayam Project Dn | |
4 | JM 2021-22 - Vellavoor Panchayath - Phase IV - Package 1-Supplying and laying distribution lines and providing FHTCs. | Kottayam Project Dn | |
5 | Package I - JJM Vellavorr panchayat | Kottayam Project Dn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Feb 2022 | 18000m/22800m laying completed. 387/1500 FHTC completed and in progress. PWD rejected 2 roads under DLP and are included in the estimate for new packages with GI as per the direction of MLA and the pipes were relocated to other panchayath roads. | Kottayam Project Dn AE1 | |
10 Nov 2021 | 9626m/22800m Laying completed. 341/1500 fhtc given. Work in progress where PWD issued sanction. Rejected 3 Roads due to DLP. Contractors request for extending time of completion up to 31/03/2022 expectin sabrimala seasonal ban on road cutting up to 15/01/2022 forwarded to higher office | Kottayam Project Dn AE1 | |
09 Nov 2021 | Contractor given request for time extension upto 31.03.2022 | Kottayam Project Dn EE | |
01 Oct 2021 | Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. | Kottayam AE 3 | |
10 Sep 2021 | 7894m/22800m Laying completed. 341/1500 fhtc given Balance can be done after getting the road cutting sanction from PWD. RR charges remitted and expecting before 15th September. | Kottayam Project Dn AE1 |
Review Date | Review Message | Review Attended By |
---|---|---|
24 Jun 2021 | Add dated photographs Documents related to road issues | EE,AEE,AE |
11 Feb 2021 | ADD PACKAGE II | AE,EE |
Date of start of Project | 21/11/2020 |
---|---|
Scheduled date of Completion of the Project | 05 May 2021 |
Expected date of Completion | 29/06/2023 |
AS Date | 21 Aug 2020 |
---|---|
TS Date | 08 Sep 2020 |
Project Officers | View |
---|