Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Feb 2022 18000m/22800m laying completed. 387/1500 FHTC completed and in progress. PWD rejected 2 roads under DLP and are included in the estimate for new packages with GI as per the direction of MLA and the pipes were relocated to other panchayath roads. Kottayam Project Dn AE1
10 Nov 2021 9626m/22800m Laying completed. 341/1500 fhtc given. Work in progress where PWD issued sanction. Rejected 3 Roads due to DLP. Contractors request for extending time of completion up to 31/03/2022 expectin sabrimala seasonal ban on road cutting up to 15/01/2022 forwarded to higher office Kottayam Project Dn AE1
09 Nov 2021 Contractor given request for time extension upto 31.03.2022 Kottayam Project Dn EE
01 Oct 2021 Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. Kottayam AE 3
10 Sep 2021 7894m/22800m Laying completed. 341/1500 fhtc given Balance can be done after getting the road cutting sanction from PWD. RR charges remitted and expecting before 15th September. Kottayam Project Dn AE1
26 Aug 2021 341/1500 fhtc given, 7894m/22800m Laying completed . Expecting pwd road cutting sanction by after mansoon ban . Hon MLA Dr N jayaraj conducted combined meeting of PWD and KWA at ponkunnam civil station. EE, AEE of PWD were present. EE agreed give road cutting sanction after 15 august depending upon the rain intensity. after getting road cutting sanction the progress of the work can be achieved Kottayam Project Dn AE1
13 Jul 2021 Meeting chaired by hon MLA Dr ണ Jayaraj conducted on 12/7/21 at PWD guest house. PWD Roads and N H Aee and AE of sections were present. The road cutting issue was arised by EE kwa in the meeting. The cutting sanction for roads where road restoration charge already remiited were discussed. AEE assured to give cutting sanction to roads in consultation with PWD EE.. But for few roads sanction is kept pending with pwd Kottayam Project Dn AE1
25 Jun 2021 7894 mts //22800 mts pipe laid, 341 nos/1500 nos FHTC given, RR charges remitted to PWD . Sanction order and agreement with PWD pending due to lockdown restrictions and further Mansoon ban on road cutting.Due to lock down and containment restriction contractor couldnot able to geo tag the connection fully hence . 307 nos geo tagged out of 350 connections. Time extension requested by the contractor. Project evaluation with Panchayath commitee Chaired by Hon.MLA Dr. N Jayaraj conducted. Kottayam Project Dn AE1
11 Jun 2021 7894 mts //22800 mts pipe laid, 341 nos/1500 nos FHTC given, RR charges remitted to PWD . Sanction order and agreement with PWD pending due to lockdown restrictions Kottayam Project Dn AE1
04 Jun 2021 7894 mts //22800 mts pipe laid, 341 nos/1500 nos FHTC given, RR charges remitted to PWD . Sanction order and agreement with PWD pending due to lockdown restrictions Kottayam Project Dn AE1