JJM- 2020-21 - VELLAVOOR PANCHAYATH- KOTTAYAM DISTRICT - Phase I- PACKAGE 2 - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I - Road Restoration of PWD roads after pipe laying

Project JJM- 2020-21 - VELLAVOOR PANCHAYATH- KOTTAYAM DISTRICT - Phase I- PACKAGE 2 - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I - Road Restoration of PWD roads after pipe laying
Project Code KTMJJM08204284P2
Type Package
Main Project JJM 2020-21- Vellavoor Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM- 2020-21 - VELLAVOOR PANCHAYATH- KOTTAYAM DISTRICT - Phase I- PACKAGE 2 - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I - Road Restoration of PWD roads after pipe laying
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 94170000
TS Number TS/2021-2022/2022/1651
Technical specification SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I - Road Restoration of PWD roads after pipe laying
Contractor M D ASHOKAN (Mob: 9846248705)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/10/2022
Scheduled date of Completion as per agreement 23 Jun 2023
Expected date of Completion 31/12/2023

Processing Dates

TS Date 03 Mar 2022
Estimate Approval 03 Mar 2022
NIT Approval 08 Jun 2022
Tender Closing 22 Aug 2022
Technichal Pre-Qualification 06 Sep 2022
Price bid opening 16 Sep 2022

Approval Dates

Workorder Date 24 Sep 2022
NA 07 Oct 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Proj Dn AE4
Date: 26/06/2024

Work in progress | 35% Completed

Pipe laying work in progress. Pending permission for Manimala- Kulathoormoozhy (1km-80GI/M, 2.5km -90/cl-5&6) KRFB road and Karukachal - Manimala PWD road (2.2km -90PVC /cl 5, 300m ,400mmDI) .

Kottayam Proj Dn AE4
Date: 25/06/2024

Work in progress | 35% Completed

Pipe laying work in progress. Pending permission for Manimala- Kulathoormoozhy (1km-80GI/M, 2.5km -90/cl-5&6) KRFB road and Karukachal - Manimala PWD road (2.2km -90PVC /cl 5, 300m ,400mmDI) .