Project | JJM- 2020-21 - KOTTAYAM DISTRICT - WSS TO VELLAVOOR PANCHAYAT - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I, ZONE - I DMA II and III - Package 4 |
---|---|
Project Code | KTMJJM08204284P4 |
Type | Package |
Main Project | JJM 2020-21- Vellavoor Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM- 2020-21 - KOTTAYAM DISTRICT - WSS TO VELLAVOOR PANCHAYAT - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I, ZONE - I DMA II and III - Package 4 |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 39000000 |
TS Number | TS/2022-2023/2022/4108 |
Technical specification | SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTCs IN VELLAVOOR PHASE I, ZONE - I DMA II and III |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 12/07/2022 |
---|---|
Scheduled date of Completion as per agreement | 29 Jun 2023 |
Expected date of Completion | 31/03/2023 |
TS Date | 20 May 2022 |
---|---|
Estimate Approval | 20 May 2022 |
NIT Approval | 20 May 2022 |
Tender Closing | 21 May 2022 |
Technichal Pre-Qualification | 25 May 2022 |
Price bid opening | 09 Jun 2022 |
Workorder Date | 30 Jun 2022 |
---|---|
NA | 12 Jul 2022 |
Kottayam Proj Dn AE4 |
Date: 26/06/2024 |
Work in progress | 65% Completed
Pipe laying completed expect for pending permission for Manimala- Kulathoormoozhy KRFB road Widening.(6KM ,150DIK9,RIDER 90PVC CL5) .
Kottayam Proj Dn AE4 |
Date: 25/06/2024 |
Work in progress | 65% Completed
Pipe laying completed expect for pending permission for Manimala- Kulathoormoozhy KRFB road Widening.(6KM ,150DIK9,RIDER 90PVC CL5) .