JJM- Kannur District - Pattiam Panchayat - WSS to Kuthuparamba Municipality, Kottayam and Pattiam Panchayaths - Phase II
Project |
JJM- Kannur District - Pattiam Panchayat - WSS to Kuthuparamba Municipality, Kottayam and Pattiam Panchayaths - Phase II |
Project Code |
KNRJJM08202943 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing 2810 Nos FHTC in Pattiam Panchayath |
Status |
On-going |
District |
Kannur |
Executing Office |
Kannur WS Dn |
AS Amount (Rs) |
112400000
|
AS Number |
GO(Rt)No.541/2020/WRD |
TS Amount (Rs) |
96700000 |
TS Number |
TS/2020-2021/2020/25370, TS/2020-2021/2020/25450 |
Total Bill Submitted (Rs) |
12640000 |
Total Bill Paid (Rs) |
12640000 |
Population Benefitted |
12500 |
Capacity in MLD |
3.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Population Benefitted---12500 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-BALANCE WORK OF LAYING DISTRIBUTION NETWORK AND PROVIDING FHTCS IN PATTIAM PANCHAYATH-Pattiam Village- WSS to Kuthuparamba Municipality, Kottayam and Pattiam Panchayaths(Pattiam Village) - Phase II - Laying Distribution System and providing FHTCs-Balance Work-Pipeline Work |
Koothuparambu PH Sn |
|
2 |
JJM- Kannur District - Pattiam Panchayat - WSS to Kuthuparamba Municipality, Kottayam and Pattiam Panchayaths - Phase II- Zone II- Kongatta and adjoining wards |
Keezhallur PH Sn |
|
3 |
JJM- Kannur District - Pattiam Panchayat - WSS to Kuthuparamba Municipality, Kottayam and Pattiam Panchayaths - Phase II- Zone I- Muthiyanga and adjoining wards |
Koothuparambu PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
11 Km of pipeline laid, 264 nos of HTCs given,117 FHTCS given |
Koothuparambu PH Sn AE |
|
18 Jun 2024 |
11 Km of pipeline laid, 274 nos of HTCs given,107 FHTCS given. |
Koothuparambu PH Sn AE |
|
06 Jun 2024 |
10.5 Km of pipeline laid, 280 nos of HTCs given,101 FHTCS given. |
Koothuparambu PH Sn AE |
|
30 May 2024 |
10.5 Km of pipeline laid, 302 nos of HTCs given,79 FHTCS given. |
Koothuparambu PH Sn AE |
|
21 May 2024 |
10.5 Km of pipeline laid, 310 nos of HTCs given,71 FHTCS given. |
Koothuparambu PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/01/2021 |
Scheduled date of Completion of the Project |
10 Feb 2024 |
Expected date of Completion |
10/02/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
27 Aug 2020 |