Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Jun 2024 | 11 Km of pipeline laid, 264 nos of HTCs given,117 FHTCS given | Koothuparambu PH Sn AE | |
18 Jun 2024 | 11 Km of pipeline laid, 274 nos of HTCs given,107 FHTCS given. | Koothuparambu PH Sn AE | |
06 Jun 2024 | 10.5 Km of pipeline laid, 280 nos of HTCs given,101 FHTCS given. | Koothuparambu PH Sn AE | |
30 May 2024 | 10.5 Km of pipeline laid, 302 nos of HTCs given,79 FHTCS given. | Koothuparambu PH Sn AE | |
21 May 2024 | 10.5 Km of pipeline laid, 310 nos of HTCs given,71 FHTCS given. | Koothuparambu PH Sn AE | |
13 May 2024 | Pipes supllied, 10.5 Km of pipeline laid, 310 nos of HTCs given | Koothuparambu PH Sn AE | |
06 May 2024 | Pipes supllied, 9.5 Km of pipeline laid, 290 nos of HTCs given | Koothuparambu PH Sn AE | |
30 Apr 2024 | Pipes supllied, 9.0 Km of pipeline laid, 280 nos of HTCs given | Koothuparambu PH Sn AE | |
22 Apr 2024 | Pipes supllied, 8.5 Km of pipeline laid, 280 nos of HTCs given | Koothuparambu PH Sn AE | |
11 Apr 2024 | Pipes supllied, 8 Km of pipeline laid, 280 nos of HTCs given | Koothuparambu PH Sn AE |