JJM- Kannur District - Pattiam Panchayat - WSS to Kuthuparamba Municipality, Kottayam and Pattiam Panchayaths - Phase II- Zone I- Muthiyanga and adjoining wards

Project JJM- Kannur District - Pattiam Panchayat - WSS to Kuthuparamba Municipality, Kottayam and Pattiam Panchayaths - Phase II- Zone I- Muthiyanga and adjoining wards
Project Code KNRJJM08202943P2
Type Package
Main Project JJM- Kannur District - Pattiam Panchayat - WSS to Kuthuparamba Municipality, Kottayam and Pattiam Panchayaths - Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM- Kannur District - Pattiam Panchayat - WSS to Kuthuparamba Municipality, Kottayam and Pattiam Panchayaths - Phase II- Zone I -Muthiyanga and adjoining wards, 1100 FHTCs and DI pipe line and Rider main line laying included in this zone.
Status On-going
District Kannur
Executing Office Koothuparambu PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 51500000
TS Number TS/2020-2021/2020/25370
Technical specification Providing FHTCs and Laying distribution line of 90mm, 75mm, 63mm and 50mm pvc pipes
Contractor N REGHU (Mob: 9496354807)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/01/2021
Scheduled date of Completion as per agreement 18 Apr 2021
Expected date of Completion 31/03/2022

Processing Dates

TS Date 27 Aug 2020
Estimate Approval 27 Aug 2020
NIT Approval 02 Nov 2020
Tender Closing 09 Nov 2020
Price bid opening 11 Nov 2020

Approval Dates

Workorder Date 18 Dec 2020
NA 04 Jan 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koothuparambu PH Sn AE
Date: 13/07/2022

Work has been completed | 100% Completed

Target Numbers of Fhtcs completed.

Koothuparambu PH Sn AE
Date: 15/06/2022

Work has been completed | 100% Completed

Target Numbers of Fhtcs completed.