- Home
- JJM 2020-21- Supplying, laying, testing,...
JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II
Project |
JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II |
Project Code |
PKDJJM09219393 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II |
Status |
On-going |
District |
Palakkad |
Executing Office |
Shornur PH Dn |
AS Amount (Rs) |
91300000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
75700000 |
TS Number |
TS/2021-2022/2020/27208 |
Total Bill Submitted (Rs) |
42370961 |
Total Bill Paid (Rs) |
42370961 |
Population Benefitted |
27971 |
Capacity in MLD |
6.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
2370nos |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Additional work of Pipe line Extension - Utilizing balance fund of JJM-In kulukkallur panchayath-Pipeline Work |
Pattambi PH Sn |
|
2 |
Jal Jeevan Mission (JJM)-Nellaya - Mappattukara PWD Road Restoration -JJM Kulukkallur Phase 2 for laying 300mm DI Pipe from Marayamangalam to Mappattukara.-General Civil Work |
Pattambi PH Sn |
|
3 |
JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II |
Pattambi PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Feb 2024 |
Pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 5000m, 2035 FHTCs given out of 2370 nos , 300mm DI Pipe stored at site |
Shornur PH Dn EE |
|
06 Feb 2023 |
Pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 4000m, 1400 FHTCs given out of 2370 nos
|
Shornur PH Dn EE |
|
27 Dec 2022 |
Pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 3000m, 1340 FHTCs given out of 2370 nos
|
Shornur PH Dn EE |
|
11 Oct 2022 |
FHTC 902 given |
Shoranur PH Sub Dn AEE |
|
30 Jun 2022 |
90 mm PE pipe laid-12000 m
FHTCs given - 493 |
Shoranur PH Sub Dn AEE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/03/2022 |
Scheduled date of Completion of the Project |
01 Sep 2022 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
25 Nov 2021 |