Jal Jeevan Mission (JJM)-Nellaya - Mappattukara PWD Road Restoration -JJM Kulukkallur Phase 2 for laying 300mm DI Pipe from Marayamangalam to Mappattukara.-General Civil Work

Project Jal Jeevan Mission (JJM)-Nellaya - Mappattukara PWD Road Restoration -JJM Kulukkallur Phase 2 for laying 300mm DI Pipe from Marayamangalam to Mappattukara.-General Civil Work
Project Code PKDJJM09219393P2
Type Package
Main Project JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Nellaya - Mappattukara PWD Road Restoration -JJM Kulukkallur Phase 2 for laying 300mm DI Pipe from Marayamangalam to Mappattukara.-General Civil Work
Status On-going
District Palakkad
Executing Office Pattambi PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 5983500
TS Number TS/10137/2023_5_1_1
Technical specification laying 300mm DI Pipe from Marayamangalam to Mappattukara

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/12/2023
Scheduled date of Completion as per agreement 22 Jan 2024
Expected date of Completion 29/02/2024

Processing Dates

TS Date 27 Nov 2023
Estimate Approval 27 Nov 2023
NIT Approval 22 Dec 2023
Tender Closing 28 Dec 2023
Technichal Pre-Qualification 22 Dec 2023
Price bid opening 29 Dec 2023

Approval Dates

Workorder Date 12 Jan 2024
NA 17 Jan 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Pattambi PH Sn AE
Date: 26/06/2024

Work has started | 0% Completed

work not started . DI pipe laying work not yet completed.

Pattambi PH Sn AE
Date: 22/06/2024

Work has started | 0% Completed

work not started . DI pipe laying work not yet completed. .