Project | Jal Jeevan Mission (JJM)-Nellaya - Mappattukara PWD Road Restoration -JJM Kulukkallur Phase 2 for laying 300mm DI Pipe from Marayamangalam to Mappattukara.-General Civil Work |
---|---|
Project Code | PKDJJM09219393P2 |
Type | Package |
Main Project | JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-Nellaya - Mappattukara PWD Road Restoration -JJM Kulukkallur Phase 2 for laying 300mm DI Pipe from Marayamangalam to Mappattukara.-General Civil Work |
Status | On-going |
District | Palakkad |
Executing Office | Pattambi PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 5983500 |
TS Number | TS/10137/2023_5_1_1 |
Technical specification | laying 300mm DI Pipe from Marayamangalam to Mappattukara |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 12/12/2023 |
---|---|
Scheduled date of Completion as per agreement | 22 Jan 2024 |
Expected date of Completion | 29/02/2024 |
TS Date | 27 Nov 2023 |
---|---|
Estimate Approval | 27 Nov 2023 |
NIT Approval | 22 Dec 2023 |
Tender Closing | 28 Dec 2023 |
Technichal Pre-Qualification | 22 Dec 2023 |
Price bid opening | 29 Dec 2023 |
Workorder Date | 12 Jan 2024 |
---|---|
NA | 17 Jan 2024 |
Pattambi PH Sn AE |
Date: 26/06/2024 |
Work has started | 0% Completed
work not started . DI pipe laying work not yet completed.
Pattambi PH Sn AE |
Date: 22/06/2024 |
Work has started | 0% Completed
work not started . DI pipe laying work not yet completed. .