Project | JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II |
---|---|
Project Code | PKDJJM09219393P1 |
Type | Package |
Main Project | JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II |
Status | On-going |
District | Palakkad |
Executing Office | Pattambi PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 75700000 |
TS Number | TS/2021-2022/2020/27208 |
Technical specification | 2370nos |
Contractor | HUNIFA MEETHAL (Mob: 9746924449) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 02/03/2022 |
---|---|
Scheduled date of Completion as per agreement | 01 Sep 2022 |
Expected date of Completion | 31/03/2024 |
TS Date | 25 Nov 2021 |
---|---|
Estimate Approval | 25 Nov 2021 |
Tender Closing | 23 Nov 2021 |
Price bid opening | 26 Nov 2021 |
Workorder Date | 02 Mar 2022 |
---|---|
NA | 14 Mar 2022 |
Pattambi PH Sn AE |
Date: 26/06/2024 |
Work in progress | 93% Completed
pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 5000m, 2050 FHTCs given out of 2370 nos , 300mm DI Pipe (3030m) work ongoing (2901m laid) .
Pattambi PH Sn AE |
Date: 22/06/2024 |
Work in progress | 90% Completed
pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 5000m, 2050 FHTCs given out of 2370 nos , 300mm DI Pipe work ongoing (2901m laid) .