Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II

Project JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II
Project Code PKDJJM09219393P1
Type Package
Main Project JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM 2020-21- Supplying, laying, testing, commissioning and mace of distribution system and mace of distribution system and providing FHTCs (2370nos) in Kulukkallur Grama Panchayath- Phase II
Status On-going
District Palakkad
Executing Office Pattambi PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 75700000
TS Number TS/2021-2022/2020/27208
Technical specification 2370nos
Contractor HUNIFA MEETHAL (Mob: 9746924449)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 02/03/2022
Scheduled date of Completion as per agreement 01 Sep 2022
Expected date of Completion 31/03/2024

Processing Dates

TS Date 25 Nov 2021
Estimate Approval 25 Nov 2021
Tender Closing 23 Nov 2021
Price bid opening 26 Nov 2021

Approval Dates

Workorder Date 02 Mar 2022
NA 14 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Pattambi PH Sn AE
Date: 26/06/2024

Work in progress | 93% Completed

pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 5000m, 2050 FHTCs given out of 2370 nos , 300mm DI Pipe (3030m) work ongoing (2901m laid) .

Pattambi PH Sn AE
Date: 22/06/2024

Work in progress | 90% Completed

pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 5000m, 2050 FHTCs given out of 2370 nos , 300mm DI Pipe work ongoing (2901m laid) .