Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Feb 2024 | Pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 5000m, 2035 FHTCs given out of 2370 nos , 300mm DI Pipe stored at site | Shornur PH Dn EE | |
06 Feb 2023 | Pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 4000m, 1400 FHTCs given out of 2370 nos | Shornur PH Dn EE | |
27 Dec 2022 | Pipe line extension 90mm HDPE -14000M(Total-14Km) , 80mm Gi pipe laying 3000m, 1340 FHTCs given out of 2370 nos | Shornur PH Dn EE | |
11 Oct 2022 | FHTC 902 given | Shoranur PH Sub Dn AEE | |
30 Jun 2022 | 90 mm PE pipe laid-12000 m FHTCs given - 493 | Shoranur PH Sub Dn AEE | |
03 Jun 2022 | 9500 m pipe laid, 420 FHTC given | Shoranur PH Sub Dn AEE | |
08 May 2022 | 11% work completed. 274 FHTCs given out of 2370 FHTCs. 2000m pipe laid. Work in progress. | Shornur PH Dn EE | |
25 Apr 2022 | 5% work completed. 120 FHTCs given out of 2370 FHTCs. Work in progress. | Shornur PH Dn EE | |
18 Apr 2022 | 120 FHTCs given out of 2370 FHTCs. Work in progress. | Shornur PH Dn EE | |
25 Mar 2022 | Work not started. Pipes are not received after TPI. | Shornur PH Dn EE |