Jeevan Mission PhasJale II - Package II - Construction of 6 m dia well ,intake channel , aproach road ,7 LL OHSR Vattamparambu , 16 LL OHSR KALAMPAABA , Interconection work and Compound wall in Kodur pt in Malappuram Dt -Part I A

Project Jeevan Mission PhasJale II - Package II - Construction of 6 m dia well ,intake channel , aproach road ,7 LL OHSR Vattamparambu , 16 LL OHSR KALAMPAABA , Interconection work and Compound wall in Kodur pt in Malappuram Dt -Part I A
Project Code MLPJJM09219072P2
Type Package
Main Project Jal Jeevan Mission Phase II-2021-22 - Providing Functional House hold tap connection to Kodur Panchayath in Malappuram District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Construction 6.00 m dia intake well, Construction of OHSR'7 LL, intake channel, approach bridge and bank protection work, Construction of 16 LL OHSR,Interconnection work and Compound wall,
Status On-going
District Malappuram
Executing Office Malappuram Sn 1
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number 9525/2022-23
Technical specification Construction of 8.00 m dia intake well, Intake channel, Approach bridge, Construction of 7.00 LL OHSR at Vattappramba, Construction of 16.00 LL OHSR at Kalanpramba, interconnection work with Pumping mains etc.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/12/2022
Scheduled date of Completion as per agreement 05 Mar 2024
Expected date of Completion 05/05/2024

Processing Dates

TS Date 08 Jul 2022
Estimate Approval 08 Jul 2022
NIT Approval 08 Jul 2022
Tender Closing 28 Oct 2022
Technichal Pre-Qualification 15 Oct 2022
Price bid opening 15 Oct 2022

Approval Dates

Workorder Date 06 Dec 2022
NA 19 Dec 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Sn AE 1
Date: 24/06/2024

Work in progress | 44% Completed

Side wall 4th lift concrete completed and plastering work in progress for 16 LL tank at Kalanparamba. Pump house work completed except some minor finishing work and electrification work. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started..

Malappuram Sn AE 1
Date: 20/06/2024

Work in progress | 44% Completed

Side wall 4th lift concrete completed for 16 LL tank at Kalanparamba. Pump house work completed except some minor finishing work and electrification work. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started..