- Home
- Jeevan Mission PhasJale II - Package II...
Jeevan Mission PhasJale II - Package II - Construction of 6 m dia well ,intake channel , aproach road ,7 LL OHSR Vattamparambu , 16 LL OHSR KALAMPAABA , Interconection work and Compound wall in Kodur pt in Malappuram Dt -Part I A
Project |
Jeevan Mission PhasJale II - Package II - Construction of 6 m dia well ,intake channel , aproach road ,7 LL OHSR Vattamparambu , 16 LL OHSR KALAMPAABA , Interconection work and Compound wall in Kodur pt in Malappuram Dt -Part I A |
Project Code |
MLPJJM09219072P2 |
Type |
Package |
Main Project |
Jal Jeevan Mission Phase II-2021-22 - Providing Functional House hold tap connection to Kodur Panchayath in Malappuram District
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Construction 6.00 m dia intake well, Construction of OHSR'7 LL, intake channel, approach bridge and bank protection work, Construction of 16 LL OHSR,Interconnection work and Compound wall, |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Sn 1 |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
|
TS Number |
9525/2022-23 |
Technical specification |
Construction of 8.00 m dia intake well, Intake channel, Approach bridge, Construction of 7.00 LL OHSR at Vattappramba, Construction of 16.00 LL OHSR at Kalanpramba, interconnection work with Pumping mains etc. |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
12/12/2022 |
Scheduled date of Completion as per agreement |
05 Mar 2024 |
Expected date of Completion |
05/05/2024 |
Processing Dates
TS Date |
08 Jul 2022 |
Estimate Approval |
08 Jul 2022 |
NIT Approval |
08 Jul 2022 |
Tender Closing |
28 Oct 2022 |
Technichal Pre-Qualification |
15 Oct 2022 |
Price bid opening |
15 Oct 2022 |
Approval Dates
Workorder Date |
06 Dec 2022 |
NA |
19 Dec 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Malappuram Sn AE 1 |
Date: 24/06/2024 |
Work in progress | 44% Completed
Side wall 4th lift concrete completed and plastering work in progress for 16 LL tank at Kalanparamba. Pump house work completed except some minor finishing work and electrification work. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started..
Malappuram Sn AE 1 |
Date: 20/06/2024 |
Work in progress | 44% Completed
Side wall 4th lift concrete completed for 16 LL tank at Kalanparamba. Pump house work completed except some minor finishing work and electrification work. The Panchayath authorities not peg marked location for & LL OHSR and hence, the work not started..