Project | Jal Jeevan Mission Phase II - Package I - Pump sets, Tansformers, RWPM, CWPM and distribution system |
---|---|
Project Code | MLPJJM09219072P1 |
Type | Package |
Main Project | Jal Jeevan Mission Phase II-2021-22 - Providing Functional House hold tap connection to Kodur Panchayath in Malappuram District |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | RW pump sets - 2 Nos, Transformers at intake and WTP, Laying RW PM, CW pump sets - 2 Nos, CW Pumping main to Vattapparamba, CW pumping main to Kalanparamba, Laying distribution network and providing Balance FHtC's |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Sn 1 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 634600000 |
TS Number | 9525/2022-2023 |
Technical specification | RW pump sets - 90 HP VT Pump sets - 2 Nos, Transformers at intake and WTP, Laying 400 mm RW PM from NK padi to WTP , 40 HP centrifugal CW pump sets - 2 Nos, 200 mm CW Pumping main from WTP site at Kalanparambu to OHSR Vattapparamba, CW pumping main to Kalanparamba, Laying distribution network and providing Balance FHtC's. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/11/2022 |
---|---|
Scheduled date of Completion as per agreement | 03 May 2024 |
Expected date of Completion | 31/03/2024 |
TS Date | 08 Jul 2022 |
---|---|
Estimate Approval | 18 Jan 2022 |
NIT Approval | 18 Jan 2022 |
Tender Closing | 24 Sep 2022 |
Technichal Pre-Qualification | 27 Sep 2022 |
Price bid opening | 27 Sep 2022 |
Workorder Date | 04 Nov 2022 |
---|---|
NA | 15 Nov 2022 |
Malappuram Sn AE 1 |
Date: 24/06/2024 |
Work in progress | 39% Completed
942m of 400mm DI pumping main at west Kodur, 850 m of 250mm DI distribution line at Mundakode, 2000 m of 200mm DI pumping main and 90mm rider at Mundakode, 1226m of 200mm DI Distribution line along with 1226m of 90mm rider at Vataparambu, 18236m of 90mm, 2450m of 110mm, 723m of 140mm, 2836m of 160mm and 728m of 180mm HDPE pipes laying in progress. Pipe laying work in progress. More pipes arriving. 450 HTC geotagged and going on. No ISA functioning in panchayath. Pipe testing almost completed. The Panchayath members and public raising objections to dig road for pipe line..
Malappuram Sn AE 1 |
Date: 20/06/2024 |
Work in progress | 39% Completed
942m of 400mm DI pumping main at west Kodur, 850 m of 250mm DI distribution line at Mundakode, 2000 m of 200mm DI pumping main and 90mm rider at Mundakode, 1226m of 200mm DI Distribution line along with 1226m of 90mm rider at Vataparambu, 18236m of 90mm, 2450m of 110mm, 723m of 140mm, 2836m of 160mm and 728m of 180mm HDPE pipes laying in progress. Pipe laying work in progress. More pipes arriving. 450 HTC geotagged and going on. No ISA functioning in panchayath. Pipe testing almost completed. The Panchayath members and public raising objections to dig road for pipe line..