Jal Jeevan Mission Phase II - Package I - Pump sets, Tansformers, RWPM, CWPM and distribution system

Project Jal Jeevan Mission Phase II - Package I - Pump sets, Tansformers, RWPM, CWPM and distribution system
Project Code MLPJJM09219072P1
Type Package
Main Project Jal Jeevan Mission Phase II-2021-22 - Providing Functional House hold tap connection to Kodur Panchayath in Malappuram District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description RW pump sets - 2 Nos, Transformers at intake and WTP, Laying RW PM, CW pump sets - 2 Nos, CW Pumping main to Vattapparamba, CW pumping main to Kalanparamba, Laying distribution network and providing Balance FHtC's
Status On-going
District Malappuram
Executing Office Malappuram Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 634600000
TS Number 9525/2022-2023
Technical specification RW pump sets - 90 HP VT Pump sets - 2 Nos, Transformers at intake and WTP, Laying 400 mm RW PM from NK padi to WTP , 40 HP centrifugal CW pump sets - 2 Nos, 200 mm CW Pumping main from WTP site at Kalanparambu to OHSR Vattapparamba, CW pumping main to Kalanparamba, Laying distribution network and providing Balance FHtC's.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/11/2022
Scheduled date of Completion as per agreement 03 May 2024
Expected date of Completion 31/03/2024

Processing Dates

TS Date 08 Jul 2022
Estimate Approval 18 Jan 2022
NIT Approval 18 Jan 2022
Tender Closing 24 Sep 2022
Technichal Pre-Qualification 27 Sep 2022
Price bid opening 27 Sep 2022

Approval Dates

Workorder Date 04 Nov 2022
NA 15 Nov 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Sn AE 1
Date: 24/06/2024

Work in progress | 39% Completed

942m of 400mm DI pumping main at west Kodur, 850 m of 250mm DI distribution line at Mundakode, 2000 m of 200mm DI pumping main and 90mm rider at Mundakode, 1226m of 200mm DI Distribution line along with 1226m of 90mm rider at Vataparambu, 18236m of 90mm, 2450m of 110mm, 723m of 140mm, 2836m of 160mm and 728m of 180mm HDPE pipes laying in progress. Pipe laying work in progress. More pipes arriving. 450 HTC geotagged and going on. No ISA functioning in panchayath. Pipe testing almost completed. The Panchayath members and public raising objections to dig road for pipe line..

Malappuram Sn AE 1
Date: 20/06/2024

Work in progress | 39% Completed

942m of 400mm DI pumping main at west Kodur, 850 m of 250mm DI distribution line at Mundakode, 2000 m of 200mm DI pumping main and 90mm rider at Mundakode, 1226m of 200mm DI Distribution line along with 1226m of 90mm rider at Vataparambu, 18236m of 90mm, 2450m of 110mm, 723m of 140mm, 2836m of 160mm and 728m of 180mm HDPE pipes laying in progress. Pipe laying work in progress. More pipes arriving. 450 HTC geotagged and going on. No ISA functioning in panchayath. Pipe testing almost completed. The Panchayath members and public raising objections to dig road for pipe line..