Jal jeevan mission -WSS to pavaratty and mullassery panchayaths in Chavakkad Taluk (Phase 2)-Balance works -State plan -supplying,Laying,Testing,and commissioning 300/250/200 mm DI K9 gravity main from chattukulam to pavaratty and mullassery OHSR including Railway push through level cross at Brahmakulam -300 mm DI Interconnection work from chittattukara Kundukadavu road,250mm DI Interconnection work from Koompully bridge and 300mm DI Pipe laying work from Pavaratty junction to Pavaratty church
Project |
Jal jeevan mission -WSS to pavaratty and mullassery panchayaths in Chavakkad Taluk (Phase 2)-Balance works -State plan -supplying,Laying,Testing,and commissioning 300/250/200 mm DI K9 gravity main from chattukulam to pavaratty and mullassery OHSR including Railway push through level cross at Brahmakulam -300 mm DI Interconnection work from chittattukara Kundukadavu road,250mm DI Interconnection work from Koompully bridge and 300mm DI Pipe laying work from Pavaratty junction to Pavaratty church |
Project Code |
TCRJJM082013846 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal jeevan mission(JJM) -WSS to pavaratty and mullassery panchayaths in Chavakkad Taluk (Phase 2)-Balance works -State plan -supplying,Laying,Testing,and commissioning 300/250/200 mm DI K9 gravity main from chattukulam to pavaratty and mullassery OHSR including Railway push through level cross at Brahmakulam -300 mm DI Interconnection work from chittattukara Kundukadavu road,250mm DI Interconnection work from Koompully bridge and 300mm DI Pipe laying work from Pavaratty junction to Pavaratty church |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
115500000
|
AS Number |
G.O.(Rt)No.541/2020/WRD |
TS Amount (Rs) |
3820000 |
TS Number |
6451/2022-2023 |
Total Bill Submitted (Rs) |
1454469 |
Total Bill Paid (Rs) |
1454469 |
Population Benefitted |
42000 |
Capacity in MLD |
4.89 |
Actual Project Completion Date |
Date is not specified |
Coverage |
All wards in Pavaratty and Mullassery Panchayaths |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--300mm DI & 250mm DI K9 pipe laying work from Pavaratty Church to Koombully 1-Pipeline Work |
Nattika Project Dn |
|
2 |
Jal Jeevan Mission (JJM)-WSS to Pavaratty&Mullasserypanchayaths in Chavakkad Taluk (Phase 2)-Balance works -Stateplan -Supplying,Laying,Testing and commissioning 300/250/200 mm DI K9 Gravity main from Chattukulam to pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam -LSGD Road Restoration charges for 20mm open graded Chipping carpet -General civil works |
Nattika Project Dn |
|
3 |
Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--Laying of HDPE Pipe PE100,PN12.5,315mmdia conforming to IS 4984/2016,using 500mm dia MS casing pipe of 10mm thick(to a minimum depth of 3m from GL)by Horizontal Directional Drilling method(railway crossing)-Pipeline Work |
Nattika Project Dn |
|
4 |
Laying 300 mm DI Interconnection work from chittattukara kundukadavu road,250 mm DI interconnection work from Koompully bridge and 300 mm DI pipe laying work from Pavaratty junction to Pavaratty church. |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
20 May 2024 |
Pavaratty and Mullassery panchayaths- road restoration GSB and WMM completed, Chipping carpet Road restoration completed in Pavaratty and Mullassery panchayath 2. Pipe laying from Pavaratty Junction to Church completed and road restoration completed and road hand over to PWD. 3. Pipe laying and Road restoration completed from Koombully to Pavaratty Church , tank interconnection work completed. 4. Boring completed near railway crossing, 300m DI pipe laying work ongoing, cumulative: 146.65m laid , Concreting work of valve chamber (north&south side) completed. Scour valve chamber work at south side completed. HDPE pipe railway crossing work, 18.8 m laid. Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing. |
Nattika Project Dn AE 2 |
|
19 May 2024 |
Pavaratty and Mullassery panchayaths- road restoration GSB and WMM completed, Chipping carpet Road restoration completed in Pavaratty and Mullassery panchayath 2. Pipe laying from Pavaratty Junction to Church completed and road restoration completed and road hand over to PWD. 3. Pipe laying and Road restoration completed from Koombully to Pavaratty Church , tank interconnection work completed. 4. Boring completed near railway crossing, 300m DI pipe laying work ongoing, cumulative: 146.65m laid , Concreting work of valve chamber (north&south side) completed. Scour valve chamber work at south side completed. HDPE pipe railway crossing work, 18.8 m laid. Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing. |
Nattika Project Dn AE 2 |
|
18 May 2024 |
Pavaratty and Mullassery panchayaths- road restoration GSB and WMM completed, Chipping carpet Road restoration completed in Pavaratty and Mullassery panchayath 2. Pipe laying from Pavaratty Junction to Church completed and road restoration completed and road hand over to PWD. 3. Pipe laying and Road restoration completed from Koombully to Pavaratty Church , tank interconnection work completed. 4. Boring completed near railway crossing, 300m DI pipe laying work ongoing, cumulative: 146.65m laid , Concreting work of valve chamber (north&south side) completed. Scour valve chamber work at south side completed. HDPE pipe railway crossing work, 18.8 m laid. Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing. |
Nattika Project Dn AE 2 |
|
17 May 2024 |
Pavaratty and Mullassery panchayaths- road restoration GSB and WMM completed, Chipping carpet Road restoration completed in Pavaratty and Mullassery panchayath 2. Pipe laying from Pavaratty Junction to Church completed and road restoration completed and road hand over to PWD. 3. Pipe laying and Road restoration completed from Koombully to Pavaratty Church , tank interconnection work completed. 4. Boring completed near railway crossing, 300m DI pipe laying work ongoing, cumulative: 146.65m laid , Concreting work of valve chamber (north&south side) completed. Scour valve chamber work at south side completed. HDPE pipe railway crossing work, 18.8 m laid. Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing. |
Nattika Project Dn AE 2 |
|
16 May 2024 |
Pavaratty and Mullassery panchayaths- road restoration GSB and WMM completed, Chipping carpet Road restoration completed in Pavaratty and Mullassery panchayath 2. Pipe laying from Pavaratty Junction to Church completed and road restoration completed and road hand over to PWD. 3. Pipe laying and Road restoration completed from Koombully to Pavaratty Church , tank interconnection work completed. 4. Boring completed near railway crossing, 300m DI pipe laying work ongoing, cumulative: 146.65m laid , Concreting work of valve chamber (north&south side) completed. Scour valve chamber work at south side completed. HDPE pipe railway crossing work, 18.8 m laid. Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing. |
Nattika Project Dn AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/02/2023 |
Scheduled date of Completion of the Project |
31 Mar 2023 |
Expected date of Completion |
10/06/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
23 Nov 2022 |