Project | Jal Jeevan Mission (JJM)-WSS to Pavaratty&Mullasserypanchayaths in Chavakkad Taluk (Phase 2)-Balance works -Stateplan -Supplying,Laying,Testing and commissioning 300/250/200 mm DI K9 Gravity main from Chattukulam to pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam -LSGD Road Restoration charges for 20mm open graded Chipping carpet -General civil works |
---|---|
Project Code | TCRJJM082013846P3 |
Type | Package |
Main Project | Jal jeevan mission -WSS to pavaratty and mullassery panchayaths in Chavakkad Taluk (Phase 2)-Balance works -State plan -supplying,Laying,Testing,and commissioning 300/250/200 mm DI K9 gravity main from chattukulam to pavaratty and mullassery OHSR including Railway push through level cross at Brahmakulam -300 mm DI Interconnection work from chittattukara Kundukadavu road,250mm DI Interconnection work from Koompully bridge and 300mm DI Pipe laying work from Pavaratty junction to Pavaratty church |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-WSS to Pavaratty&Mullasserypanchayaths in Chavakkad Taluk (Phase 2)-Balance works -Stateplan -Supplying,Laying,Testing and commissioning 300/250/200 mm DI K9 Gravity main from Chattukulam to pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam -LSGD Road Restoration charges for 20mm open graded Chipping carpet -General civil works |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 19400000 |
TS Number | 15629/2022-2023 |
Technical specification | -LSGD Road Restoration charges for 20mm open graded Chipping carpet |
Contractor | CIJOE P S (Mob: 9446322577) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 27/05/2023 |
---|---|
Scheduled date of Completion as per agreement | 04 Oct 2023 |
Expected date of Completion | 27/10/2023 |
TS Date | 07 Mar 2023 |
---|---|
Estimate Approval | 21 Feb 2023 |
NIT Approval | 24 Feb 2023 |
Tender Closing | 08 Mar 2023 |
Technichal Pre-Qualification | 17 Mar 2023 |
Price bid opening | 23 Mar 2023 |
Workorder Date | 05 Apr 2023 |
---|---|
NA | 24 Apr 2023 |
Nattika Project Dn EE |
Date: 24/01/2024 |
Work has been completed | 100% Completed
Road restoration -Chipping carpet in Pavaratty and Mullassery panchayath work completed..
Nattika Project Dn EE |
Date: 23/01/2024 |
Work in progress | 94% Completed
Road restoration -Chipping carpet completed in Pavaratty panchayath, Mullassery panchayath restoration ongoing..