Project | Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--300mm DI & 250mm DI K9 pipe laying work from Pavaratty Church to Koombully 1-Pipeline Work |
---|---|
Project Code | TCRJJM082013846P2 |
Type | Package |
Main Project | Jal jeevan mission -WSS to pavaratty and mullassery panchayaths in Chavakkad Taluk (Phase 2)-Balance works -State plan -supplying,Laying,Testing,and commissioning 300/250/200 mm DI K9 gravity main from chattukulam to pavaratty and mullassery OHSR including Railway push through level cross at Brahmakulam -300 mm DI Interconnection work from chittattukara Kundukadavu road,250mm DI Interconnection work from Koompully bridge and 300mm DI Pipe laying work from Pavaratty junction to Pavaratty church |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--300mm DI & 250mm DI K9 pipe laying work from Pavaratty Church to Koombully 1-Pipeline Work |
Status | On-going |
District | Thrissur |
Executing Office | Nattika Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 48400000 |
TS Number | 6451/2022-2023 |
Technical specification | 300mm DI & 250mm DI K9 pipe laying work from Pavaratty Church to Koombully 1-Pipeline Work, Pavaratty and Mullassery Tank interconnection work, Road restoration work. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/04/2023 |
---|---|
Scheduled date of Completion as per agreement | 14 Apr 2024 |
Expected date of Completion | 16/04/2024 |
TS Date | 23 Nov 2022 |
---|---|
Estimate Approval | 21 Oct 2022 |
NIT Approval | 28 Oct 2022 |
Tender Closing | 28 Nov 2022 |
Technichal Pre-Qualification | 12 Dec 2022 |
Price bid opening | 26 Dec 2022 |
Workorder Date | 17 Apr 2023 |
---|---|
NA | 28 Apr 2023 |
Nattika Project Dn AE 2 |
Date: 04/03/2024 |
Work in progress | 98% Completed
Pipe laying , road restoration and tank interconnection completed.
Nattika Project Dn AE 2 |
Date: 03/03/2024 |
Work in progress | 98% Completed
Pipe laying , road restoration and tank interconnection completed.