Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--300mm DI & 250mm DI K9 pipe laying work from Pavaratty Church to Koombully 1-Pipeline Work

Project Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--300mm DI & 250mm DI K9 pipe laying work from Pavaratty Church to Koombully 1-Pipeline Work
Project Code TCRJJM082013846P2
Type Package
Main Project Jal jeevan mission -WSS to pavaratty and mullassery panchayaths in Chavakkad Taluk (Phase 2)-Balance works -State plan -supplying,Laying,Testing,and commissioning 300/250/200 mm DI K9 gravity main from chattukulam to pavaratty and mullassery OHSR including Railway push through level cross at Brahmakulam -300 mm DI Interconnection work from chittattukara Kundukadavu road,250mm DI Interconnection work from Koompully bridge and 300mm DI Pipe laying work from Pavaratty junction to Pavaratty church
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--300mm DI & 250mm DI K9 pipe laying work from Pavaratty Church to Koombully 1-Pipeline Work
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 48400000
TS Number 6451/2022-2023
Technical specification 300mm DI & 250mm DI K9 pipe laying work from Pavaratty Church to Koombully 1-Pipeline Work, Pavaratty and Mullassery Tank interconnection work, Road restoration work.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/04/2023
Scheduled date of Completion as per agreement 14 Apr 2024
Expected date of Completion 16/04/2024

Processing Dates

TS Date 23 Nov 2022
Estimate Approval 21 Oct 2022
NIT Approval 28 Oct 2022
Tender Closing 28 Nov 2022
Technichal Pre-Qualification 12 Dec 2022
Price bid opening 26 Dec 2022

Approval Dates

Workorder Date 17 Apr 2023
NA 28 Apr 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn AE 2
Date: 04/03/2024

Work in progress | 98% Completed

Pipe laying , road restoration and tank interconnection completed.

Nattika Project Dn AE 2
Date: 03/03/2024

Work in progress | 98% Completed

Pipe laying , road restoration and tank interconnection completed.