Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--Laying of HDPE Pipe PE100,PN12.5,315mmdia conforming to IS 4984/2016,using 500mm dia MS casing pipe of 10mm thick(to a minimum depth of 3m from GL)by Horizontal Directional Drilling method(railway crossing)-Pipeline Work

Project Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--Laying of HDPE Pipe PE100,PN12.5,315mmdia conforming to IS 4984/2016,using 500mm dia MS casing pipe of 10mm thick(to a minimum depth of 3m from GL)by Horizontal Directional Drilling method(railway crossing)-Pipeline Work
Project Code TCRJJM082013846P4
Type Package
Main Project Jal jeevan mission -WSS to pavaratty and mullassery panchayaths in Chavakkad Taluk (Phase 2)-Balance works -State plan -supplying,Laying,Testing,and commissioning 300/250/200 mm DI K9 gravity main from chattukulam to pavaratty and mullassery OHSR including Railway push through level cross at Brahmakulam -300 mm DI Interconnection work from chittattukara Kundukadavu road,250mm DI Interconnection work from Koompully bridge and 300mm DI Pipe laying work from Pavaratty junction to Pavaratty church
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description WRD/KWA-CE(CR)/EST/11852/2022_26_2_1/RC 1 ] Jal Jeevan Mission (JJM)-WSS to Pavaratty & Mullassery Panchayaths in Chavakkad Taluk (Phase 2) - Balance works-State Plan -Supplying,Laying,Testing and Commissioning 300/250/200mm DI K9 Gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam--Laying of HDPE Pipe PE100,PN12.5,315mmdia conforming to IS 4984/2016,using 500mm dia MS casing pipe of 10mm thick(to a minimum depth of 3m from GL)by Horizontal Directional Drilling method(railway crossing)-Pipeline Work
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 5600000
TS Number
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 04 Oct 2023
Estimate Approval 04 Oct 2023
NIT Approval 01 Jan 2024
Tender Closing 10 Jan 2024
Price bid opening 11 Apr 2024

Approval Dates

Workorder Date 06 Feb 2024
NA 20 Feb 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn AE 2
Date: 21/05/2024

Work has been completed | 100% Completed

Work completed..

Nattika Project Dn AE 2
Date: 20/05/2024

Work in progress | 95% Completed

Valve chamber cover slab concreting and Stub bend works completed, DI & HDPE interconnection work completed and Scour chamber work ongoing..