| Project | AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS AT OLD MUNCIPAL AREA IN KOLLAM CORPORATION |
|---|---|
| Project Code | KLMAMRUT112213823P1 |
| Type | Package |
| Main Project | AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS IN KOLLAM CORPORATION |
| Funding Agency | AMRUT |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS AT OLD MUNCIPAL AREA IN KOLLAM CORPORATION |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam WS Sn 1 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 60800000 |
| TS Number | WRD/KWA-CE(SR)/EST_TS/1144/2022_26_1_1 |
| Technical specification | AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS AT OLD MUNCIPAL AREA IN KOLLAM CORPORATION |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 02/10/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 06 Jul 2024 |
| Expected date of Completion | Date is not specified |
| TS Date | 14 Feb 2023 |
|---|---|
| Estimate Approval | 13 Feb 2023 |
| NIT Approval | 13 Feb 2023 |
| Tender Closing | 17 Mar 2023 |
| Technichal Pre-Qualification | 07 Jul 2023 |
| Price bid opening | 18 Mar 2023 |
| Workorder Date | 17 Jul 2023 |
|---|---|
| NA | 07 Jul 2023 |
| Kollam WS Sn 1 - AE |
| Date: 15/10/2026 |
Work in progress | 99% Completed
95% completed, 1573nos FHTCs are given (51%), Total Pipe laid till date- 14830.1 m (99%).
| Kollam WS Sn 1 - AE |
| Date: 09/10/2026 |
Work in progress | 99% Completed
95% completed, 1573nos FHTCs are given (51%), Total Pipe laid till date- 14830.1 m (99%).