| Project | AMRUT- 2.0 RETROFIT AND PROVIDING NEW WATER CONNECTION AT SAKTHIKULANGARA AND THRIKKADAVOOR AREA UNDER KOLLAM CORPORATION-AMRUT- 2.0 RETROFIT AND PROVIDING NEW WATER CONNECTION AT SAKTHIKULANGARA AND THRIKKADAVOOR AREAS UNDER KOLLAM CORPORATION |
|---|---|
| Project Code | KLMAMRUT112213823P3 |
| Type | Package |
| Main Project | AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS IN KOLLAM CORPORATION |
| Funding Agency | AMRUT |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT- 2.0 RETROFIT AND PROVIDING NEW WATER CONNECTION AT SAKTHIKULANGARA AND THRIKKADAVOOR AREA UNDER KOLLAM CORPORATION |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam WS Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 57400000 |
| TS Number | WRD/KWA-CE(SR)/EST_TS/1091/2022_26_1_1 |
| Technical specification | Providing FHTCS and Pipe line extensions in Thrikkadavoor area and Sakthikulangara area in Kollam corporation |
| Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
|---|---|---|---|---|---|---|
| 07 Sep 2026 | Pending | Pending | Approval/Permissions Related (from other departments excluding road cut permission and land related) | Sakthikulangara & Thrikkadavoor zone FHTCs works delaying | No comments available. | Pending |
| 26 Jun 2024 | Pending | Pending | Natural Calamities Related | Sakthikulangara & Thrikkadavoor area | No comments available. | Pending |
| 20 Jun 2024 | Pending | Pending | Natural Calamities Related | Sakthikulangara & Thrikkadavoor area | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 17/05/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 10 Apr 2024 |
| Expected date of Completion | Date is not specified |
| TS Date | 19 Jan 2023 |
|---|---|
| Estimate Approval | 19 Jan 2023 |
| NIT Approval | 19 Jan 2023 |
| Tender Closing | 06 Feb 2023 |
| Technichal Pre-Qualification | 01 Mar 2023 |
| Price bid opening | 01 Mar 2023 |
| Workorder Date | 11 Apr 2023 |
|---|---|
| NA | 28 Feb 2023 |
| Kollam WS Sn 2 - AE |
| Date: 15/10/2026 |
Work in progress | 93% Completed
2159 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work.
| Kollam WS Sn 2 - AE |
| Date: 06/10/2026 |
Work in progress | 93% Completed
2159 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work .