Project | KIIFB- Kondotty - Package 3 A- Laying distribution system for Zone 1,2 &3 and laying transmission main to various service reservoirs |
---|---|
Project Code | MLPKIIFB0619570P1 |
Type | Package |
Main Project | KIIFB Project: Tranche 13: WRD004-02- lmprovements to WSS of Kondotty Municipality- Phase-ll |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Improvements to WSS to Kondotty Municipality- Phase II- Package III A- Laying distribution system for Zone 1,2 &3 and laying transmission main to various service reservoirs |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 376200000 |
TS Number | 5127/19-20 |
Technical specification | work covers the supplying, laying, testing and commissioning of 124.87 km distribution pipe lines comprising 160mm PVC class 4 to class 6 and 150 mm & 80mm GI pipes. Supplying and laying distribution system including fixing of all pipes, specials, required valves and construction of valve chambers, anchor blocks, interconnection with existing 200 mm DI to 400 mm DI pipes wherever necessary, and other connected works . The distribution system also includes the supplying, laying, testing and commissioning of DI pipes for a length of 154 meters. and supplying, laying, testing and commissioning of 200mm, 250mm and 300mm DI Gravity mains for length of 9260 meters. |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
12 Feb 2020 | Pending | Pending | Road Cut Related Risk | road cutting permission not obtained from NHAI palakkad for laying pipe line from chainage KM 25/400 to 35/000 of NH 966 | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 03/04/2020 |
---|---|
Scheduled date of Completion as per agreement | 12 Dec 2021 |
Expected date of Completion | 28/02/2023 |
TS Date | 05 Nov 2019 |
---|---|
Estimate Approval | 05 Nov 2019 |
NIT Approval | 20 Nov 2019 |
Tender Closing | 31 Jan 2020 |
Technichal Pre-Qualification | 18 Feb 2020 |
Price bid opening | 19 Feb 2020 |
Workorder Date | 13 Mar 2020 |
---|---|
NA | 03 Apr 2020 |
Malappuram Project Dn AE6 |
Date: 11/05/2023 |
Work has been completed | 100% Completed
Termination of contract by the superintending engineer PH circle Malappuram as per court Judgement of the Hon'ble High Court of Kerala WP © No. 18521/2022 dt.22.06.2022.and final bill prepared..
Malappuram Project Dn AE6 |
Date: 10/05/2023 |
Work in progress | 96% Completed
The pipe laying work of zone 1 and zone 2 is completed and charged. pipe laying work of zone almost pipe laying work completed all roads except NH road for 19Km for non getting permission from NHAI. Now this work is in stand still . Contractor approached high court for decision. .