Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB- Kondotty - Package 3 A- Laying distribution system for Zone 1,2 &3 and laying transmission main to various service reservoirs

Project KIIFB- Kondotty - Package 3 A- Laying distribution system for Zone 1,2 &3 and laying transmission main to various service reservoirs
Project Code MLPKIIFB0619570P1
Type Package
Main Project KIIFB Project: Tranche 13: WRD004-02- lmprovements to WSS of Kondotty Municipality- Phase-ll
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Improvements to WSS to Kondotty Municipality- Phase II- Package III A- Laying distribution system for Zone 1,2 &3 and laying transmission main to various service reservoirs
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 376200000
TS Number 5127/19-20
Technical specification work covers the supplying, laying, testing and commissioning of 124.87 km distribution pipe lines comprising 160mm PVC class 4 to class 6 and 150 mm & 80mm GI pipes. Supplying and laying distribution system including fixing of all pipes, specials, required valves and construction of valve chambers, anchor blocks, interconnection with existing 200 mm DI to 400 mm DI pipes wherever necessary, and other connected works . The distribution system also includes the supplying, laying, testing and commissioning of DI pipes for a length of 154 meters. and supplying, laying, testing and commissioning of 200mm, 250mm and 300mm DI Gravity mains for length of 9260 meters.

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
12 Feb 2020 Pending Pending Road Cut Related Risk road cutting permission not obtained from NHAI palakkad for laying pipe line from chainage KM 25/400 to 35/000 of NH 966 No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 03/04/2020
Scheduled date of Completion as per agreement 12 Dec 2021
Expected date of Completion 28/02/2023

Processing Dates

TS Date 05 Nov 2019
Estimate Approval 05 Nov 2019
NIT Approval 20 Nov 2019
Tender Closing 31 Jan 2020
Technichal Pre-Qualification 18 Feb 2020
Price bid opening 19 Feb 2020

Approval Dates

Workorder Date 13 Mar 2020
NA 03 Apr 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE6
Date: 11/05/2023

Work has been completed | 100% Completed

Termination of contract by the superintending engineer PH circle Malappuram as per court Judgement of the Hon'ble High Court of Kerala WP © No. 18521/2022 dt.22.06.2022.and final bill prepared..

Malappuram Project Dn AE6
Date: 10/05/2023

Work in progress | 96% Completed

The pipe laying work of zone 1 and zone 2 is completed and charged. pipe laying work of zone almost pipe laying work completed all roads except NH road for 19Km for non getting permission from NHAI. Now this work is in stand still . Contractor approached high court for decision. .