KIIFB Kondotty-Package 2A- Construction of 14LL Capacity OHSR at Kumbalapara, supplying and laying pumping main from WTP to Kumbalapara, laying gravity mains to various reserviours, supply, errection and commiisioning of clear water pump set at WTP site

Project KIIFB Kondotty-Package 2A- Construction of 14LL Capacity OHSR at Kumbalapara, supplying and laying pumping main from WTP to Kumbalapara, laying gravity mains to various reserviours, supply, errection and commiisioning of clear water pump set at WTP site
Project Code MLPKIIFB0619570P4
Type Package
Main Project KIIFB Project: Tranche 13: WRD004-02- lmprovements to WSS of Kondotty Municipality- Phase-ll
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB Kondotty-Package 2A- Construction of 14LL Capacity OHSR at Kumbalapara, supplying and laying pumping main from WTP to Kumbalapara, laying gravity mains to various reserviours, supply, errection and commiisioning of clear water pump set at WTP site
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 149000000
TS Number 9135/20-21
Technical specification Construction of 14LL Capacity OHSR at Kumbalapara, supplying and laying pumping main from WTP to Kumbalapara, laying gravity mains to various reserviours, supply, errection and commiisioning of clear water pump set at WTP site

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/02/2021
Scheduled date of Completion as per agreement 31 Mar 2022
Expected date of Completion 28/02/2023

Processing Dates

TS Date 13 Oct 2020
Estimate Approval 13 Oct 2020
NIT Approval 20 Oct 2020
Tender Closing 16 Nov 2020
Technichal Pre-Qualification 08 Dec 2020
Price bid opening 25 Dec 2020

Approval Dates

Workorder Date 23 Jan 2021
NA 09 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE6
Date: 04/05/2024

Work in progress | 99% Completed

14.00LL OHSR work completed , Laying 350mm pumping main for 14.60km completed .

Malappuram Project Dn AE6
Date: 03/05/2024

Work in progress | 99% Completed

14.00LL OHSR work completed , Laying 350mm pumping main for 14.60km completed .