JJM-Kumaramangalam Panchayath-Providing Functional Household Tap Connections (FHTC) to all households of Kumaramangalam panchayath in Idukki District
Project |
JJM-Kumaramangalam Panchayath-Providing Functional Household Tap Connections (FHTC) to all households of Kumaramangalam panchayath in Idukki District |
Project Code |
IDKJJM08207361 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing Functional Household Tap Connections (FHTC) to all households of Kumaramangalam panchayath in Idukki District.
1) Providing fhtc to all households, renovation of old WTP, construction of OHSR and providing clear water pumps of RWSS to Kumaramangalam panchayath in Idukki district.
2) Supplying and laying Distribution lines in Zone_I,Construction of 2.10LL Capacity Sump cum PH at Choozhamkudipara and Road Restoration works.
3) Supply and laying of 250mm DI K9 Clear Water Gravity Main and Distribution lines In Zone-II. |
Status |
On-going |
District |
Idukki |
Executing Office |
Kattappana Project Dn |
AS Amount (Rs) |
172200000
|
AS Number |
GO(Rt)541/2020/WRD dtd 21/08/2020 |
TS Amount (Rs) |
1345100000 |
TS Number |
12527/2020-2021 |
Total Bill Submitted (Rs) |
141271465 |
Total Bill Paid (Rs) |
141271465 |
Population Benefitted |
17875 |
Capacity in MLD |
3.00 |
Actual Project Completion Date |
31 Mar 2022 |
Coverage |
All wards of Kumaramangalam Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission– Kumaramangalam-Providing Functional Household Tap Connections (FHTC) to all households, renovation of old WTP, Construction of OHSR and Providing Clear water pumps of RWSS to Kumaramangalam panchayath in Idukki District. |
Project Division Kattapana |
|
2 |
JJM- KUMARAMANGALAM- 03&08-PROVIDING FHTC TO ALL HOUSEHOLDS OF KUMARAMANGALAM PANCHAYATH IN IDUKKI DISTRICT- Supply and laying of 250mm DI K9 Clear Water Gravity Main and Distribution lines In Zone-II |
Project Division Kattapana |
|
3 |
JJM-Kumaramangalm-Providing Functional Household Tap Connections (FHTC) to all households-Supplying and laying Distribution lines in Zone_I,Construction of 2.10LL Capacity Sump cum PH at Choozhamkudipara and Road Restoration works |
Project Division Kattapana |
|
4 |
JJM - WSS TO KUMARAMANGALAM PANCHAYATH IN IDUKKI DISTRICT - PIPE LINE EXTENSION FOR VARIOUS WARDS IN KUMARAMANGALAM PANCHAYATH |
Project Division Kattapana |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Jul 2023 |
65mm GI pipe laying works ongoing |
Kattapana Project Dn AE4 |
|
15 Jun 2023 |
65mm GI pipe laying works |
Kattapana Project Dn AE4 |
|
12 Jun 2023 |
65mm gi pipe laying work |
Kattapana Project Dn AE4 |
|
07 Jun 2023 |
pipe line extension works in progress and Ladder work completed |
Kattapana Project Dn AE4 |
|
05 Jun 2023 |
pipe line extension works in progress and Ladder work to be undertaken |
Kattapana Project Dn AE4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/02/2021 |
Scheduled date of Completion of the Project |
31 Mar 2021 |
Expected date of Completion |
10/04/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
18 Nov 2020 |