JJM-Kumaramangalam Panchayath-Providing Functional Household Tap Connections (FHTC) to all households of Kumaramangalam panchayath in Idukki District

Project JJM-Kumaramangalam Panchayath-Providing Functional Household Tap Connections (FHTC) to all households of Kumaramangalam panchayath in Idukki District
Project Code IDKJJM08207361
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing Functional Household Tap Connections (FHTC) to all households of Kumaramangalam panchayath in Idukki District. 1) Providing fhtc to all households, renovation of old WTP, construction of OHSR and providing clear water pumps of RWSS to Kumaramangalam panchayath in Idukki district. 2) Supplying and laying Distribution lines in Zone_I,Construction of 2.10LL Capacity Sump cum PH at Choozhamkudipara and Road Restoration works. 3) Supply and laying of 250mm DI K9 Clear Water Gravity Main and Distribution lines In Zone-II.
Status On-going
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 172200000
AS Number GO(Rt)541/2020/WRD dtd 21/08/2020
TS Amount (Rs) 1345100000
TS Number 12527/2020-2021
Total Bill Submitted (Rs) 141271465
Total Bill Paid (Rs) 141271465
Population Benefitted 17875
Capacity in MLD 3.00
Actual Project Completion Date 31 Mar 2022
Coverage All wards of Kumaramangalam Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission– Kumaramangalam-Providing Functional Household Tap Connections (FHTC) to all households, renovation of old WTP, Construction of OHSR and Providing Clear water pumps of RWSS to Kumaramangalam panchayath in Idukki District. Project Division Kattapana
2 JJM- KUMARAMANGALAM- 03&08-PROVIDING FHTC TO ALL HOUSEHOLDS OF KUMARAMANGALAM PANCHAYATH IN IDUKKI DISTRICT- Supply and laying of 250mm DI K9 Clear Water Gravity Main and Distribution lines In Zone-II Project Division Kattapana
3 JJM-Kumaramangalm-Providing Functional Household Tap Connections (FHTC) to all households-Supplying and laying Distribution lines in Zone_I,Construction of 2.10LL Capacity Sump cum PH at Choozhamkudipara and Road Restoration works Project Division Kattapana
4 JJM - WSS TO KUMARAMANGALAM PANCHAYATH IN IDUKKI DISTRICT - PIPE LINE EXTENSION FOR VARIOUS WARDS IN KUMARAMANGALAM PANCHAYATH Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Jul 2023 65mm GI pipe laying works ongoing Kattapana Project Dn AE4
15 Jun 2023 65mm GI pipe laying works Kattapana Project Dn AE4
12 Jun 2023 65mm gi pipe laying work Kattapana Project Dn AE4
07 Jun 2023 pipe line extension works in progress and Ladder work completed Kattapana Project Dn AE4
05 Jun 2023 pipe line extension works in progress and Ladder work to be undertaken Kattapana Project Dn AE4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 18/02/2021
Scheduled date of Completion of the Project 31 Mar 2021
Expected date of Completion 10/04/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 18 Nov 2020