JJM-Kumaramangalm-Providing Functional Household Tap Connections (FHTC) to all households-Supplying and laying Distribution lines in Zone_I,Construction of 2.10LL Capacity Sump cum PH at Choozhamkudipara and Road Restoration works

Project JJM-Kumaramangalm-Providing Functional Household Tap Connections (FHTC) to all households-Supplying and laying Distribution lines in Zone_I,Construction of 2.10LL Capacity Sump cum PH at Choozhamkudipara and Road Restoration works
Project Code IDKJJM08207361P2
Type Package
Main Project JJM-Kumaramangalam Panchayath-Providing Functional Household Tap Connections (FHTC) to all households of Kumaramangalam panchayath in Idukki District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Description Supplying and laying Distribution lines in Zone_I,Construction of 2.10LL Capacity Sump cum PH at Choozhamkudipara and Road Restoration works
Status On-going
District Idukki
Executing Office Kattappana Project Dn
TS Amount (Rs) 60600000
TS Number TS/2020-2021/2020/20167
Technical specification Supplying and laying Distribution lines in Zone_I,Construction of 2.10LL Capacity Sump cum PH at Choozhamkudipara and Road Restoration works

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 18/02/2021
Scheduled date of Completion as per agreement 31 Mar 2021
Expected date of Completion 31/12/2021

Processing Dates

TS Date 18 Nov 2020
Estimate Approval 18 Nov 2020
NIT Approval 20 Nov 2020
Tender Closing 15 Dec 2020
Technichal Pre-Qualification 17 Dec 2020
Price bid opening 23 Dec 2020

Approval Dates

Workorder Date 24 Jan 2021
Agreement Date 18 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

Kattapana Project Dn AE4
Date: 25/07/2021

Work in progress | 16% Completed

Distribution system- work in progress. Sump cum pump house- completed the levelling concrete of Sump.

Kattapana Project Dn AE4
Date: 22/07/2021

Work in progress | 16% Completed

Distribution system- work in progress. Sump cum pump house- completed the levelling concrete of Sump.