Jal Jeevan Mission– Kumaramangalam-Providing Functional Household Tap Connections (FHTC) to all households, renovation of old WTP, Construction of OHSR and Providing Clear water pumps of RWSS to Kumaramangalam panchayath in Idukki District.

Project Jal Jeevan Mission– Kumaramangalam-Providing Functional Household Tap Connections (FHTC) to all households, renovation of old WTP, Construction of OHSR and Providing Clear water pumps of RWSS to Kumaramangalam panchayath in Idukki District.
Project Code IDKJJM08207361P1
Type Package
Main Project JJM-Kumaramangalam Panchayath-Providing Functional Household Tap Connections (FHTC) to all households of Kumaramangalam panchayath in Idukki District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing Functional Household Tap Connections (FHTC) to all households, renovation of old WTP, Construction of OHSR and Providing Clear water pumps of RWSS to Kumaramangalam panchayath in Idukki District.
Status On-going
District Idukki
Executing Office Kattappana Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 45600000
TS Number 12527/2020-2021
Technical specification Providing Functional Household Tap Connections (FHTC) to all households, renovation of old WTP, Construction of OHSR and Providing Clear water pumps of RWSS to Kumaramangalam panchayath in Idukki District.
Contractor M/s Majestic Constructions (Mob: 9447043876)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/02/2021
Scheduled date of Completion as per agreement 31 Mar 2021
Expected date of Completion 31/12/2022

Processing Dates

TS Date 23 Dec 2020
Estimate Approval 23 Dec 2020
NIT Approval 31 Dec 2020
Tender Closing 18 Jan 2021
Technichal Pre-Qualification 27 Jan 2021
Price bid opening 02 Feb 2021

Approval Dates

Workorder Date 15 Feb 2021
NA 18 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattapana Project Dn AE4
Date: 07/06/2023

Work has been completed | 100% Completed

ladder work completed.

Kattapana Project Dn AE4
Date: 05/06/2023

Work in progress | 99% Completed

Ladder work to be undertaken at OHSR.