| Project | JJM- KUMARAMANGALAM- 03&08-PROVIDING FHTC TO ALL HOUSEHOLDS OF KUMARAMANGALAM PANCHAYATH IN IDUKKI DISTRICT- Supply and laying of 250mm DI K9 Clear Water Gravity Main and Distribution lines In Zone-II |
|---|---|
| Project Code | IDKJJM08207361P3 |
| Type | Package |
| Main Project | JJM-Kumaramangalam Panchayath-Providing Functional Household Tap Connections (FHTC) to all households of Kumaramangalam panchayath in Idukki District |
| Funding Agency | JJM |
| Category | JJM | Type of scheme | Water Supply |
| Description | Supply and laying of 250mm DI K9 Clear Water Gravity Main and Distribution lines In Zone-II |
| Status | On-going |
| District | Idukki |
| Executing Office | Kattappana Project Dn |
| TS Amount (Rs) | 35900000 |
| TS Number | 11170/2020-2021 |
| Technical specification | Supply and laying of 250mm DI K9 Clear Water Gravity Main and Distribution lines In Zone-II |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 03/05/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Jun 2021 |
| Expected date of Completion | 31/12/2021 |
| TS Date | 22 Nov 2020 |
|---|---|
| Estimate Approval | 21 Aug 2020 |
| NIT Approval | 22 Nov 2021 |
| Tender Closing | 23 Dec 2021 |
| Technichal Pre-Qualification | 23 Dec 2020 |
| Price bid opening | 08 Feb 2021 |
| Workorder Date | 26 Feb 2021 |
|---|---|
| Agreement Date | 05 May 2021 |
| Kattapana Project Dn AE4 |
| Date: 25/07/2021 |
Work in progress | 2% Completed
Pipe was supplied partially. Road cutting sanction is processing.
| Kattapana Project Dn AE4 |
| Date: 22/07/2021 |
Work in progress | 2% Completed
Pipe was supplied partially. Road cutting sanction is processing.