Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn
09 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn
08 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn
07 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn
06 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn
04 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn
03 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn
02 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn
01 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn
29 Nov 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn