| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied . Pipe laying in progress. | Nattika Project Dn AE 6 | |
| 23 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied . Pipe laying in progress. | Nattika Project Dn AE 6 | |
| 22 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied . Pipe laying in progress. | Nattika Project Dn AE 6 | |
| 21 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied . | Nattika Project Dn AE 6 | |
| 20 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied .Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 6 | |
| 19 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied .Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 6 | |
| 18 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied .Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 6 | |
| 17 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied .Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 6 | |
| 16 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied .Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 6 | |
| 14 Sep 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. 500mm DI - 990m pipe supplied .Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 6 |