| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.55 km pipe laying completed | Nattika Project Dn | |
| 21 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.55 km pipe laying completed | Nattika Project Dn | |
| 19 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.55 km pipe laying completed | Nattika Project Dn | |
| 18 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.55 km pipe laying completed | Nattika Project Dn | |
| 17 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.55 km pipe laying completed | Nattika Project Dn | |
| 16 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.55 km pipe laying completed | Nattika Project Dn | |
| 15 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.55 km pipe laying completed | Nattika Project Dn | |
| 14 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.55 km pipe laying completed | Nattika Project Dn | |
| 11 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.27 km pipe laying completed | Nattika Project Dn | |
| 10 Feb 2022 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 28.27 km pipe laying completed | Nattika Project Dn |