| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Dec 2021 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. | Nattika Project Dn | |
| 30 Dec 2021 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. | Nattika Project Dn | |
| 29 Dec 2021 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. | Nattika Project Dn | |
| 24 Dec 2021 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. | Nattika Project Dn | |
| 22 Dec 2021 | intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. | Nattika Project Dn | |
| 21 Dec 2021 | ntake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. | Nattika Project Dn | |
| 20 Dec 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Restoration work started Pavartty raech | Nattika Project Dn | |
| 17 Dec 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Restoration work started Pavartty raech | Nattika Project Dn | |
| 14 Dec 2021 | Road cutting permission Chavakkad- wadakkenchery road obtained FROM PWD order noA4-5424/18/EE DATED 09/12/2021 | Nattika Project Dn | |
| 13 Dec 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain | Nattika Project Dn |