Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Dec 2021 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Nattika Project Dn
30 Dec 2021 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Nattika Project Dn
29 Dec 2021 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Nattika Project Dn
24 Dec 2021 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Nattika Project Dn
22 Dec 2021 intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Nattika Project Dn
21 Dec 2021 ntake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Nattika Project Dn
20 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Restoration work started Pavartty raech Nattika Project Dn
17 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Restoration work started Pavartty raech Nattika Project Dn
14 Dec 2021 Road cutting permission Chavakkad- wadakkenchery road obtained FROM PWD order noA4-5424/18/EE DATED 09/12/2021 Nattika Project Dn
13 Dec 2021 Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying delayed due to continuous heavy rain Nattika Project Dn