Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Dec 2023 | Pipe Laid 3752 m out of 19200m. | Kannur WS Sn AE 2 | |
24 Dec 2023 | Pipe Laid 3151m out of 19200m | Kannur WS Sn AE 2 | |
21 Dec 2023 | Pipe Laid 3055m out of 19200m. | Kannur WS Sn AE 2 | |
18 Dec 2023 | Pipe Laid 2016m out of 19200m. | Kannur WS Sn AE 2 | |
15 Dec 2023 | Pipe Laid 2016m out of 19200m. | Kannur WS Sn AE 2 | |
12 Dec 2023 | PIPE LAYING WORK STARTED. | Kannur WS Sn AE 2 | |
06 Dec 2023 | PIPE LAYING WORK STARTED. | Kannur WS Sn AE 2 | |
03 Dec 2023 | PIPE LAYING WORK STARTED. | Kannur WS Sn AE 2 | |
03 Dec 2023 | Pipe not supplied | Kannur WS Sn AE 2 | |
30 Nov 2023 | Pipe not supplied. | Kannur WS Sn AE 2 |