Status Date Overall Project Status Project Officer Contact
26 Jan 2024 Pipe Laid 11000 m out of 19200m. Kannur WS Sn AE 2
23 Jan 2024 Pipe Laid 9500 m out of 19200m. Kannur WS Sn AE 2
20 Jan 2024 Pipe Laid 8899 m out of 19200m. Kannur WS Sn AE 2
17 Jan 2024 Pipe Laid 7800 m out of 19200m. Kannur WS Sn AE 2
14 Jan 2024 Pipe Laid 7280 m out of 19200m. Kannur WS Sn AE 2
11 Jan 2024 Pipe Laid 6692 m out of 19200m. Kannur WS Sn AE 2
08 Jan 2024 Pipe Laid 6392 m out of 19200m. Kannur WS Sn AE 2
05 Jan 2024 Pipe Laid 5402 m out of 19200m. Kannur WS Sn AE 2
02 Jan 2024 Pipe Laid 5252 m out of 19200m. Kannur WS Sn AE 2
30 Dec 2023 Pipe Laid 4252 m out of 19200m. Kannur WS Sn AE 2