AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - ELAYAVOOR ZONE- Pipeline work

Project AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - ELAYAVOOR ZONE- Pipeline work
Project Code KNRAMRUT 2032314163
Type Main project
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - ELAYAVOOR ZONE- Pipeline work
Status On-going
District Kannur
Executing Office Kannur WS Dn
AS Amount (Rs) 699900000
AS Number G. O(Rt)No. 677/2023/LSGD
TS Amount (Rs) 93300000
TS Number WRD/KWA-CE(NR)/EST_TS/10536/2022_26_2_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 12500
Capacity in MLD 1.50
Actual Project Completion Date Date is not specified
Coverage PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - ELAYAVOOR ZONE- Pipeline work

Packages

No. Project Name Location View
1 AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - ELAYAVOOR ZONE- Pipeline work Kannur WS Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Jun 2024 pipe Laid 13350m out of 19200m and FHTC 795 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
14 Jun 2024 pipe Laid 13350m out of 19200m and FHTC 795 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
11 Jun 2024 pipe Laid 13350m out of 19200m and FHTC 795 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
08 Jun 2024 pipe Laid 13350m out of 19200m and FHTC 795 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
05 Jun 2024 Pipe Laid 13350m out of 19200m and FHTC 790 Nos out of 2500 Nos completed. Kannur WS Sn AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/08/2023
Scheduled date of Completion of the Project 29 Feb 2024
Expected date of Completion 30/09/2024

Processing Dates

AS Date 21 Mar 2023
TS Date 10 Apr 2023

Other details

Project Officers View