Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Apr 2024 | Pipe Laid 13350m out of 19200m and FHTC 780 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
20 Apr 2024 | Pipe Laid 13350m out of 19200m and FHTC 780 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
17 Apr 2024 | Pipe Laid 13350m out of 19200m and FHTC 450 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
14 Apr 2024 | Pipe Laid 13350m out of 19200m and FHTC 450 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
11 Apr 2024 | Pipe Laid 13350m out of 19200m and FHTC 450 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
08 Apr 2024 | Pipe Laid 13350m out of 19200m and FHTC 450 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
05 Apr 2024 | Pipe Laid 13350m out of 19200m and FHTC 450 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
02 Apr 2024 | Pipe Laid 13050 m out of 19200m. | Kannur WS Sn AE 2 | |
30 Mar 2024 | Pipe Laid 13050 m out of 19200m. | Kannur WS Sn AE 2 | |
27 Mar 2024 | Pipe Laid 13050 m out of 19200m. | Kannur WS Sn AE 2 |