Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Sep 2023 | Agreement executed on 09.08.2023 and site handed over on 19.08.2023 | Kannur WS Sn AE 2 | |
05 Sep 2023 | Agreement executed on 09.08.2023 and site handed over on 19.08.2023 | Kannur PH Dn EE | |
03 Sep 2023 | Agreement executed. | Kannur WS Sn AE 2 | |
01 Sep 2023 | Agreement executed | Kannur WS Sub-Dn - AEE | |
30 Aug 2023 | WORK ORDER ISSUED, AGREEMENT EXECUTED. | Kannur WS Sn AE 2 | |
27 Aug 2023 | WORK ORDER ISSUED, AGREEMENT EXECUTED. | Kannur WS Sn AE 2 | |
24 Aug 2023 | WORK ORDER ISSUED, AGREEMENT EXECUTED. | Kannur WS Sn AE 2 | |
21 Aug 2023 | WORK ORDER ISSUED, AGREEMENT EXECUTED. | Kannur WS Sn AE 2 | |
19 Aug 2023 | WORK ORDER ISSUED, AGREEMENT EXECUTED. | Kannur WS Sn AE 2 | |
18 Aug 2023 | WORK ORDER ISSUED, AGREEMENT NOT EXECUTED. | Kannur WS Sn AE 2 |